5513 N MURIETTA AVE 91401

Certificate Information: 5513 N MURIETTA AVE 91401

Application / Permit
19047-20000-01827
Plan Check / Job No.
B19VN18607
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
(N) 32'-9"X19'-0" POOL WITH 9'-0"X9'-9" SPA PER STD PLAN 268
Permit Issued
Issued on 2/12/2020
Issuing Office
Valley
Current Status
CofO Issued on 4/10/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/28/2019 APPLICANT
Assigned to Plan Check Engineer 10/28/2019 MARVEL DELACRUZ
Corrections Issued 10/28/2019 MARVEL DELACRUZ
Issued 2/12/2020 LADBS
CofO in Progress 2/26/2021 JENNIFER RABUCHIN
No Progress 3/13/2021 MICHAEL TEMPLE
CofO in Progress 3/13/2021 MICHAEL TEMPLE
CofO Issued 4/10/2021 MICHAEL SMITH
Permit Finaled 4/10/2021 MICHAEL SMITH

Permit Application Clearance Information

Construction near power lines Cleared 10/31/2019 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/21/2020 Approved PIERRE VEGA
Rough-Plumbing 5/21/2020 Approved PIERRE VEGA
Deputy Shotcrete 5/22/2020 Conditional Approval MISAEL ESPARZA
Gas Piping or Gas Test 5/27/2020 Corrections Issued MISAEL ESPARZA
Gas Piping or Gas Test 5/29/2020 Approved MISAEL ESPARZA
Grounding or Bonding 11/9/2020 Corrections Issued JENNIFER RABUCHIN
Grounding or Bonding 11/17/2020 Not Ready for Inspection BRENDAN LOONEY
Grounding or Bonding 11/19/2020 Approved BEAU COLLINS
Enclosure/Fence 12/10/2020 Approved MICHEL ABAJAN
Equipment Noise Level 12/21/2020 Approved ALFREDO FLORES
Final 1/15/2021 Corrections Issued JOHN HAYES
Pre-Gunite 1/15/2021 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 1/15/2021 SGSOV Not Ready JOHN HAYES
Final 1/27/2021 Not Ready for Inspection BEAU COLLINS
Pre-Gunite 1/27/2021 Approved BEAU COLLINS
SGSOV-Seismic Gas S/O Valve 1/27/2021 SGSOV Approved BEAU COLLINS
Final 2/5/2021 Not Ready for Inspection DAVID SANDOVAL
Final 2/17/2021 Not Ready for Inspection JOHN HAYES
Final 2/25/2021 OK to Issue CofO JENNIFER RABUCHIN