20330 W DEL CAMPO PL 91364
Certificate Information: 20330 W DEL CAMPO PL 91364
- Application / Permit
- 19047-20000-01823
- Plan Check / Job No.
- B19VN18475
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- ADD NEW 36' X 16' SWIMMING POOL AND 8' X 8' SPA INSIDE THE SHELL OF (E) POOL PER STANDARD PLAN # 268 , CHANGE POOL DEPTH FROM 9 FT TO 6 FT PER ENGINEERING DETAIL- SEE COMMENTS
- Permit Issued
- Issued on 10/25/2019
- Issuing Office
- Valley
- Current Status
- Issued on 10/25/2019
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/25/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/25/2019 | RARES BODEA |
| Plan Check Approved | 10/25/2019 | RARES BODEA |
| Issued | 10/25/2019 | LADBS |
Permit Application Clearance Information
| ZA Case | Cleared | 10/25/2019 | RINA LARA |
Contact Information
| Contractor | Platner'S Pools; Lic. No.: 713747-C53 | 5862 CAPE HORN DRIVE AGOURA HILLS, CA 91301 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 11/7/2019 | Approved | SEAN WIRCH |
| Deck | 1/27/2020 | Approved | STEVEN BACK |
| Enclosure/Fence | 2/4/2020 | Not Ready for Inspection | STEVEN BACK |
| Enclosure/Fence | 2/18/2020 | Corrections Issued | DAVID STEPANYAN |
| Enclosure/Fence | 2/25/2020 | Approved | PETER FOLLING |
| ELECTRICAL-Final | 3/5/2020 | Not Ready for Inspection | PETER FOLLING |
| Excavation/Setback/Form/Re-Bar | 3/5/2020 | Approved | PETER FOLLING |
| Final | 3/5/2020 | Not Ready for Inspection | PETER FOLLING |
| PLUMBING-Final | 3/5/2020 | Not Ready for Inspection | PETER FOLLING |
| SGSOV-Seismic Gas S/O Valve | 3/5/2020 | SGSOV Not Ready | PETER FOLLING |
| ELECTRICAL-Final | 3/11/2020 | Approved | PETER FOLLING |
| Final | 3/11/2020 | Not Ready for Inspection | PETER FOLLING |
| PLUMBING-Final | 3/11/2020 | Approved | PETER FOLLING |
| SGSOV-Seismic Gas S/O Valve | 3/11/2020 | SGSOV Not Required | PETER FOLLING |
| Final | 3/16/2020 | Not Ready for Inspection | PETER FOLLING |
| Final | 3/20/2020 | Partial Approval | DAVID SANDOVAL |
| Pool/Spa Cover | 3/20/2020 | Approved | DAVID SANDOVAL |