640 S CURSON AVE 90036
Certificate Information: 640 S CURSON AVE 90036
- Application / Permit
- 19047-20000-01698
- Plan Check / Job No.
- B19VN16986
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- Apartment
- Primary Use
- (4) Pool/Spa - Public
- Work Description
- NEW 10'-6" X 15' SPA PER STANDARD PLAN 268 AND ENGINEERING DETAILS
- Permit Issued
- Issued on 2/21/2020
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 3/17/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/3/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/17/2019 | SELLA BENYAMIN |
| Corrections Issued | 10/21/2019 | SELLA BENYAMIN |
| Quality Review Completed | 10/21/2019 | STEVEN KIM |
| Building Plans Picked Up | 10/22/2019 | APPLICANT |
| Disabled Access Plans Picked Up | 10/22/2019 | APPLICANT |
| Plan Check Approved | 2/21/2020 | SELLA BENYAMIN |
| Issued | 2/21/2020 | LADBS |
| Permit Finaled | 3/17/2021 | EDWIN GREGORYONA |
Permit Application Clearance Information
| DAS Clearance | Cleared | 2/10/2020 | SELLA BENYAMIN |
| "Q" conditions | Cleared | 2/21/2020 | MIGUEL GAMBOA |
| Miscellaneous | Cleared | 2/21/2020 | MIGUEL GAMBOA |
| Miscellaneous | Cleared | 2/21/2020 | MIGUEL GAMBOA |
| Miscellaneous | Cleared | 2/21/2020 | MIGUEL GAMBOA |
| Miscellaneous | Cleared | 2/21/2020 | MIGUEL GAMBOA |
| Miscellaneous | Cleared | 2/21/2020 | MIGUEL GAMBOA |
| Public Swimming Pool approval | Cleared | 2/21/2020 | LACDHS APPROVED |
| Supp. Use District POD/CDO/TDO | Cleared | 2/21/2020 | MIGUEL GAMBOA |
| ZA Case | Cleared | 2/21/2020 | MIGUEL GAMBOA |
Contact Information
| Contractor | Addison Pools Inc; Lic. No.: 753417-C53 | 4363 WOODMAN AVENUE SHERMAN OAKS, CA 91423 |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| MARTIN TAVITIAN, (213) 482-7357 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Rough | 3/19/2020 | Approved | LARRY ARNICK |
| Pre-Gunite | 3/19/2020 | Approved | LARRY ARNICK |
| Excavation/Setback/Form/Re-Bar | 4/29/2020 | Approved | JONATHAN QUACH |
| METHANE-Barrier | 4/29/2020 | Approved | JONATHAN QUACH |
| METHANE-Subgrade | 4/29/2020 | Approved | JONATHAN QUACH |
| Enclosure/Fence | 12/10/2020 | Not Ready for Inspection | LARRY ARNICK |
| Final | 3/17/2021 | Permit Finaled | EDWIN GREGORYONA |
| SGSOV-Seismic Gas S/O Valve | 3/17/2021 | SGSOV Approved | EDWIN GREGORYONA |