16866 W MOONCREST DR 91436
Certificate Information: 16866 W MOONCREST DR 91436
- Application / Permit
- 19047-20000-01476
- Plan Check / Job No.
- B19VN14681
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 40'-0" X 16'-0" SWIMMING POOL AND 7'-0" X 16'-0" SPA WITHIN PER ENGINEER DESIGN
- Permit Issued
- Issued on 2/11/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/4/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/30/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/12/2019 | JEROME MAGAT PALMA |
| Corrections Issued | 9/16/2019 | JEROME MAGAT PALMA |
| Quality Review Completed | 9/17/2019 | ABDUL CHEGENI |
| Building Plans Picked Up | 9/18/2019 | APPLICANT |
| Plan Check Approved | 2/11/2020 | JEROME MAGAT PALMA |
| Issued | 2/11/2020 | LADBS |
| CofO in Progress | 8/10/2020 | RONALD COWAN |
| Permit Finaled | 9/4/2020 | DONALD SUNSERI |
| CofO Issued | 9/4/2020 | DONALD SUNSERI |
| Permit Finaled | 9/4/2020 | DONALD SUNSERI |
Permit Application Clearance Information
| Construction near power lines | Cleared | 2/11/2020 | OSCAR CASTRO |
| Grading Pre-Inspection | Cleared | 2/11/2020 | JEROME MAGAT PALMA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rybak,, Richard; Lic. No.: GE2131 | 20312 TAU PLACE CHATSWORTH, CA 91311 |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 25531 PRADO DELAS BELLOTAS CALABASAS, CA 91302 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 3/12/2020 | Approved | RONALD COWAN |
| Excavation/Setback/Form/Re-Bar | 4/21/2020 | Approved | RONALD COWAN |
| Grounding or Bonding | 4/21/2020 | Approved | RONALD COWAN |
| Pre-Gunite | 4/21/2020 | Approved | RONALD COWAN |
| Deputy Shotcrete | 4/23/2020 | Approved | RONALD COWAN |
| Gas Piping or Gas Test | 4/30/2020 | Approved | RONALD COWAN |
| Rough-Electrical | 4/30/2020 | Approved | RONALD COWAN |
| Rough-Plumbing | 4/30/2020 | Approved | RONALD COWAN |
| Enclosure/Fence | 6/22/2020 | Approved | RONALD COWAN |
| Final | 7/2/2020 | Corrections Issued | RONALD COWAN |
| SGSOV-Seismic Gas S/O Valve | 7/2/2020 | SGSOV Not Ready | RONALD COWAN |
| Equipment Noise Level | 7/8/2020 | Approved | ALFREDO FLORES |
| Final | 8/5/2020 | OK to Issue CofO | RONALD COWAN |
| SGSOV-Seismic Gas S/O Valve | 8/5/2020 | SGSOV Approved | RONALD COWAN |