3336 N LONGRIDGE AVE 91423

Certificate Information: 3336 N LONGRIDGE AVE 91423

Application / Permit
19047-20000-01368
Plan Check / Job No.
B19VN13521
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW ( 15'-7"x 27'-0") POOL & (6'-5"x 5'-0) SPA. WORK PER ENGINEER.
Permit Issued
Issued on 11/5/2019
Issuing Office
Valley
Current Status
CofO Issued on 10/19/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/13/2019 APPLICANT
Assigned to Plan Check Engineer 8/29/2019 TROY DEGUZMAN
Corrections Issued 9/3/2019 TROY DEGUZMAN
Quality Review Completed 9/6/2019 CHON CHIO KUO
Building Plans Picked Up 9/13/2019 APPLICANT
Plan Check Approved 11/5/2019 TROY DEGUZMAN
Issued 11/5/2019 LADBS
CofO in Progress 10/18/2021 CHRISTOPHE COCHRAN
CofO Issued 10/19/2021 MICHAEL SMITH
Permit Finaled 10/19/2021 MICHAEL SMITH

Permit Application Clearance Information

Miscellaneous Cleared 10/11/2019 STEVEN WECHSLER
Miscellaneous Cleared 10/11/2019 STEVEN WECHSLER
ZA Case Cleared 10/11/2019 STEVEN WECHSLER
Miscellaneous Cleared 10/15/2019 TRACY WILLIAMS
Specific Plan Cleared 10/15/2019 TRACY WILLIAMS
ZI Cleared 10/15/2019 TRACY WILLIAMS
GPI Written Notices Cleared 11/5/2019 TROY DEGUZMAN
Grading Pre-Inspection Cleared 11/5/2019 TROY DEGUZMAN

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Gas Piping or Gas Test 6/17/2021 Approved ARAM AVEDISIAN
Pre-Gunite 6/17/2021 Corrections Issued ARAM AVEDISIAN
Rough-Electrical 6/17/2021 Approved ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 7/8/2021 Approved ARAM AVEDISIAN
Grounding or Bonding 7/8/2021 Partial Approval ARAM AVEDISIAN
Pool Piping 7/8/2021 Approved ARAM AVEDISIAN
Pre-Gunite 7/8/2021 Approved ARAM AVEDISIAN
Deputy Other (see comments) 7/15/2021 Partial Approval ASHLEY THOMPSON
Deputy Shotcrete 7/15/2021 Conditional Approval CALEB MEISTER
Grounding or Bonding 7/29/2021 Approved ARAM AVEDISIAN
Enclosure/Fence 8/12/2021 Corrections Issued ARAM AVEDISIAN
Enclosure/Fence 8/13/2021 Approved ARAM AVEDISIAN
Pool Equipment Noise Test 8/24/2021 Approved FELIPE PENICHE
Final 8/27/2021 Not Ready for Inspection ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 8/27/2021 SGSOV Not Ready ARAM AVEDISIAN
Final 10/12/2021 Corrections Issued ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 10/12/2021 SGSOV Approved ARAM AVEDISIAN
Final 10/18/2021 OK to Issue CofO CHRISTOPHE COCHRAN