4229 N IRVINE AVE 91604

Certificate Information: 4229 N IRVINE AVE 91604

Application / Permit
19047-20000-01204
Plan Check / Job No.
B19VN11880
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 30' x 16' SWIMMING POOL AND 7' x 7' SPA PER STD. PLAN # 268
Permit Issued
Issued on 1/8/2020
Issuing Office
Valley
Current Status
CofO Issued on 5/5/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/18/2019 APPLICANT
Assigned to Plan Check Engineer 7/18/2019 JEFFREY TANGONAN
Corrections Issued 7/18/2019 JEFFREY TANGONAN
Plan Check Approved 1/8/2020 JEROME MAGAT PALMA
Issued 1/8/2020 LADBS
CofO in Progress 5/3/2022 THOMAS FINNILA
Permit Finaled 5/5/2022 DANIEL ORRANTE
CofO Issued 5/5/2022 DANIEL ORRANTE
Permit Finaled 5/5/2022 DANIEL ORRANTE

Permit Application Clearance Information

Construction near power lines Cleared 12/26/2019 RIDWAN HARDY

Contact Information

Contractor Custom Derian Pools; Lic. No.: 977981-C53 P O BOX 1352      MOORPARK, CA 93020

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Gas Piping or Gas Test 1/27/2020 Approved JEFFREY PARD
Grounding or Bonding 1/27/2020 Partial Approval JEFFREY PARD
Pool Piping 1/27/2020 Approved JEFFREY PARD
Pre-Gunite 1/27/2020 Approved JEFFREY PARD
Rough-Electrical 1/27/2020 Partial Approval JEFFREY PARD
Rough-Plumbing 1/27/2020 Approved JEFFREY PARD
Deputy Shotcrete 1/31/2020 Approved JEFFREY PARD
Rough-Electrical 2/13/2020 Partial Approval JEFFREY PARD
Deck 4/9/2020 Approved JEFFREY PARD
Grounding or Bonding 4/9/2020 Approved JEFFREY PARD
Enclosure/Fence 6/15/2020 Approved DANIEL DREW
ELECTRICAL-Final 6/22/2020 Not Ready for Inspection THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 6/22/2020 Approved THOMAS FINNILA
Final 6/22/2020 Corrections Issued THOMAS FINNILA
PLUMBING-Final 6/22/2020 Not Ready for Inspection THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 6/22/2020 SGSOV Not Ready THOMAS FINNILA
Pool Equipment Noise Test 6/26/2020 Approved FELIPE PENICHE
ELECTRICAL-Final 8/24/2020 Approved THOMAS FINNILA
Final 8/24/2020 Corrections Issued THOMAS FINNILA
PLUMBING-Final 8/24/2020 Corrections Issued THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 8/24/2020 SGSOV Approved THOMAS FINNILA
Final 4/27/2022 Corrections Issued ARAM AVEDISIAN
Final 5/2/2022 OK to Issue CofO THOMAS FINNILA