433 N EL MEDIO AVE 90272
Certificate Information: 433 N EL MEDIO AVE 90272
- Application / Permit
- 19047-20000-01099
- Plan Check / Job No.
- B19VN10877
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 14' X 29' POOL WITH 6'X 6' SPA PER ENGINEERING
- Permit Issued
- Issued on 9/4/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/28/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/1/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/25/2019 | SELLA BENYAMIN |
| Corrections Issued | 7/29/2019 | SELLA BENYAMIN |
| Quality Review Completed | 7/29/2019 | STEVEN KIM |
| Building Plans Picked Up | 7/30/2019 | APPLICANT |
| Plan Check Approved | 9/4/2019 | SELLA BENYAMIN |
| Issued | 9/4/2019 | LADBS |
| CofO in Progress | 7/27/2020 | ANDREW NAVE |
| CofO in Progress | 7/27/2020 | ANDREW NAVE |
| Permit Finaled | 7/28/2020 | VINCENT COTTON |
| CofO Issued | 7/28/2020 | VINCENT COTTON |
| Permit Finaled | 7/28/2020 | VINCENT COTTON |
Permit Application Clearance Information
| Coastal Zone | Cleared | 8/14/2019 | HERMINIGILDO AGUSTIN |
| Coastal Zone | Cleared | 8/14/2019 | HERMINIGILDO AGUSTIN |
| Coastal Zone | Cleared | 8/14/2019 | HERMINIGILDO AGUSTIN |
| Miscellaneous | Cleared | 8/14/2019 | HERMINIGILDO AGUSTIN |
| ZA Case | Cleared | 8/14/2019 | HERMINIGILDO AGUSTIN |
Contact Information
| Contractor | Artisan Pacific Homes Inc; Lic. No.: 961077-B | 16030 JUNALUSKA WAY PACIFIC PALISADES, CA 90272 |
| Engineer | Djoneva,, Diana Ivanova; Lic. No.: C73805 | 3241 HENRIETTA AVE LA CRESCENTA, CA 91214 |
Inspector Information
| MEL KHACHATOURIAN, (213) 796-6439 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 10/21/2019 | Corrections Issued | ANDREW NAVE |
| Rough-Electrical | 10/21/2019 | Approved | ANDREW NAVE |
| Rough-Plumbing | 10/21/2019 | Approved | ANDREW NAVE |
| Deck | 2/5/2020 | Approved | ANDREW NAVE |
| Enclosure/Fence | 6/2/2020 | Approved | ANDREW NAVE |
| Pool/Spa Cover | 6/2/2020 | Approved | ANDREW NAVE |
| Pool Equipment Noise Test | 6/16/2020 | Approved | STEVEN BELTRAN |
| Excavation/Setback/Form/Re-Bar | 6/19/2020 | Approved | ANDREW NAVE |
| Final | 6/19/2020 | Not Ready for Inspection | ANDREW NAVE |
| Pre-Gunite | 6/19/2020 | Partial Inspection | ANDREW NAVE |
| SGSOV-Seismic Gas S/O Valve | 6/19/2020 | SGSOV Not Ready | ANDREW NAVE |
| Final | 6/30/2020 | Not Ready for Inspection | ANDREW NAVE |
| Pre-Gunite | 6/30/2020 | Approved | ANDREW NAVE |
| SGSOV-Seismic Gas S/O Valve | 6/30/2020 | SGSOV Approved | ANDREW NAVE |
| Final | 7/27/2020 | OK to Issue CofO | ANDREW NAVE |