2020 N SERRANO AVE 90027

Certificate Information: 2020 N SERRANO AVE 90027

Application / Permit
19047-20000-01060
Plan Check / Job No.
B19VN10445
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 18' 6" X 24' SWIMMING POOL ON CONCRETE PILES. ALL WORK DONE PER STRUCTURAL ENGINEERING.
Permit Issued
Issued on 1/2/2020
Issuing Office
Valley
Current Status
CofO Issued on 10/2/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/21/2019 APPLICANT
Assigned to Plan Check Engineer 7/11/2019 GURUNATH NESARAJAH
Corrections Issued 7/14/2019 GURUNATH NESARAJAH
Quality Review Completed 7/16/2019 OMID HEDAYAT
Building Plans Picked Up 7/26/2019 APPLICANT
Plan Check Approved 1/2/2020 LUIS RINCON
Issued 1/2/2020 LADBS
CofO in Progress 10/1/2021 BRAD BESCOS
Permit Finaled 10/2/2021 DEROLD HAUFF
CofO Issued 10/2/2021 DEROLD HAUFF
Permit Finaled 10/2/2021 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 12/6/2019 RIDWAN HARDY
Grading Pre-Inspection Cleared 12/13/2019 GURUNATH NESARAJAH

Contact Information

Contractor Amazon Pools; Lic. No.: 830886-C53 18653 VENTURA BLVD #139      TARZANA, CA 91356
Engineer Cai,, Luo B; Lic. No.: C80352 9428 ETAON AVE M      CHATSWORTH, CA 91311
Engineer Zhang,, Yao; Lic. No.: C74572 538 ROCCO CIRCLE      CORONA, CA 92882
Geologist Tsao,, Tze-Tzong; Lic. No.: EG1783 9428 ETON AVENUE #M      CHATSWORTH, CA 91311

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 1/27/2020 Corrections Issued ROBERT CORNELL
Piling/Pier/Caisson 3/4/2020 Not Ready for Inspection RAUL BARAJAS
Piling/Pier/Caisson 3/9/2020 Partial Approval ROBERT CORNELL
Pre-Gunite 4/20/2020 Approved BRIAN SULLIVAN
Rough-Plumbing 5/29/2020 Corrections Issued JOSEPH MCGARRY
Rough-Plumbing 6/3/2020 Approved ENRIQUE MIRELES
Gas Piping or Gas Test 6/10/2020 Approved JOSEPH MCGARRY
Pool Piping 6/10/2020 Approved JOSEPH MCGARRY
Rough-Electrical 6/10/2020 Approved JOSEPH MCGARRY
Special/Order Compliance 6/10/2020 Partial Inspection JOSEPH MCGARRY
Deck 7/15/2020 Approved BRIAN SULLIVAN
Grounding or Bonding 7/15/2020 Approved BRIAN SULLIVAN
Enclosure/Fence 8/11/2020 Not Ready for Inspection ENRIQUE MIRELES
Enclosure/Fence 8/18/2020 Approved BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 10/16/2020 Approved RAUL BARAJAS
Final 10/16/2020 Corrections Issued RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 10/16/2020 SGSOV Not Ready RAUL BARAJAS
Pool Equipment Noise Test 10/19/2020 Approved ROBERT CHAVEZ
Final 10/23/2020 Corrections Issued DONALD CRICHLOW
SGSOV-Seismic Gas S/O Valve 10/23/2020 SGSOV Not Ready DONALD CRICHLOW
Final 11/16/2020 Corrections Issued COREY HUPP
SGSOV-Seismic Gas S/O Valve 11/16/2020 SGSOV Not Ready COREY HUPP
Final 11/23/2020 Conditional Approval BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 11/23/2020 SGSOV Approved BRIAN SULLIVAN
Final 9/30/2021 OK to Issue CofO BRAD BESCOS