4246 N LEVITT LANE 91403
Certificate Information: 4246 N LEVITT LANE 91403
- Application / Permit
- 19047-20000-01024
- Plan Check / Job No.
- B19VN09977
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 20' X 40' POOL W/ 8' X 8' SPA PER STANDARD PLAN #268 AND ENGINEERING DETAILS
- Permit Issued
- Issued on 4/25/2022
- Issuing Office
- Current Status
- CofO Issued on 12/27/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/14/2019 | APPLICANT |
| Green Plans Picked Up | 7/17/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/25/2019 | RAPHAEL ROSAS |
| Corrections Issued | 7/27/2019 | RAPHAEL ROSAS |
| Quality Review Completed | 8/1/2019 | CHON CHIO KUO |
| Applicant returned to address corrections | 9/26/2019 | RAPHAEL ROSAS |
| Plan Check Approved | 4/11/2022 | RAPHAEL ROSAS |
| Building Plans Picked Up | 4/12/2022 | APPLICANT |
| Issued | 4/25/2022 | APPLICANT |
| CofO in Progress | 11/30/2023 | JUAN VALENZUELA |
| Permit Finaled | 12/27/2023 | RUBEN SALAS |
| CofO Issued | 12/27/2023 | RUBEN SALAS |
| Permit Finaled | 12/27/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Miscellaneous | Cleared | 12/23/2020 | DANG NGUYEN |
| Grading Pre-Inspection | Cleared | 5/5/2021 | RAPHAEL ROSAS |
Contact Information
| Contractor | Flexi - Tech Contracting Inc; Lic. No.: 767683-C53 | 6924 CANBY AVENUE UNIT 105 RESEDA, CA 91335 |
| Engineer | Daneshfar,, Kourosh Dan; Lic. No.: C68377 | 19722 ARMINTA ST WINNETKA, CA 91306 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
| Geologist | Feffer,, Joshua Rafael; Lic. No.: EG2138 | 12253 GORHAM AVE LOS ANGELES, CA 90049 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 6/21/2022 | Approved | JACK KARGODORIAN |
| Deputy Shotcrete | 7/1/2022 | Conditional Approval | MATT KELLERMAN |
| Pool Piping | 8/19/2022 | Approved | CALEB MEISTER |
| Grounding or Bonding | 10/4/2022 | Approved | MISAEL ESPARZA |
| Gas Piping or Gas Test | 12/9/2022 | Corrections Issued | MISAEL ESPARZA |
| Rough-Electrical | 12/9/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Gas Piping or Gas Test | 3/2/2023 | Approved | MISAEL ESPARZA |
| Rough-Electrical | 3/2/2023 | Approved | MISAEL ESPARZA |
| Enclosure/Fence | 9/20/2023 | Corrections Issued | MISAEL ESPARZA |
| Enclosure/Fence | 9/26/2023 | Corrections Issued | MISAEL ESPARZA |
| Enclosure/Fence | 9/28/2023 | Approved | MISAEL ESPARZA |
| Pool Equipment Noise Test | 11/13/2023 | Approved | FELIPE PENICHE |
| Excavation/Setback/Form/Re-Bar | 11/21/2023 | Approved | MISAEL ESPARZA |
| Final | 11/21/2023 | Corrections Issued | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 11/21/2023 | SGSOV Approved | MISAEL ESPARZA |
| Final | 11/28/2023 | OK to Issue CofO | JUAN VALENZUELA |