7875 W GRANITO DR 90046
Certificate Information: 7875 W GRANITO DR 90046
- Application / Permit
- 19047-20000-00752
- Plan Check / Job No.
- B19VN00996
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- (N) POOL (93'-6" X 15') & SPA (10' X 15') ABOVE POOL EQUIPMENT ROOM
- Permit Issued
- Issued on 8/6/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 8/29/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/6/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/14/2019 | NILOOFAR MEHRAIN |
| Corrections Issued | 2/20/2019 | NILOOFAR MEHRAIN |
| Quality Review Completed | 2/22/2019 | CHON CHIO KUO |
| Building Plans Picked Up | 2/25/2019 | APPLICANT |
| Green Plans Picked Up | 2/25/2019 | APPLICANT |
| Applicant returned to address corrections | 5/8/2019 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 6/20/2019 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 7/16/2019 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 2/3/2020 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 2/26/2020 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 3/18/2020 | NILOOFAR MEHRAIN |
| Plan Check Approved | 4/7/2020 | NILOOFAR MEHRAIN |
| Issued | 8/6/2020 | APPLICANT |
| CofO in Progress | 8/4/2023 | STUART CHAPMAN |
| Permit Finaled | 8/29/2023 | DEROLD HAUFF |
| CofO Issued | 8/29/2023 | DEROLD HAUFF |
| Permit Finaled | 8/29/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/18/2020 | NILOOFAR MEHRAIN |
| Miscellaneous | Cleared | 7/8/2020 | NOAH MCCOY |
| Miscellaneous | Cleared | 7/8/2020 | NOAH MCCOY |
| Miscellaneous | Cleared | 7/8/2020 | NOAH MCCOY |
| Miscellaneous | Cleared | 7/8/2020 | NOAH MCCOY |
| Miscellaneous | Cleared | 7/8/2020 | NOAH MCCOY |
| Miscellaneous | Cleared | 7/8/2020 | NOAH MCCOY |
| Miscellaneous | Cleared | 7/8/2020 | NOAH MCCOY |
| Tract Map conditions | Cleared | 7/8/2020 | NOAH MCCOY |
| ZA Case | Cleared | 7/8/2020 | NOAH MCCOY |
| Eng Process Fee Ord 176,300 | Cleared | 7/13/2020 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 7/24/2020 | NGOC KIEM |
Contact Information
| Contractor | Hill Pete Construction Company Inc; Lic. No.: 470065-B | 4626 ALBUQUERQUE ST 2ND FLOOR SAN DIEGO, CA 92109 |
| Engineer | Labib,, Youhanna T; Lic. No.: S4549 | 319 MAIN STREET EL SEGUNDO, CA 90245 |
| Engineer | Zweigler,, Robert Ingraham; Lic. No.: GE2120 | 1461 E. CHEVY CHASE DR. #200 GLENDALE, CA 91206 |
| Geologist | Zweigler,, Robert Ingraham; Lic. No.: EG1210 | 196 DIRT ROAD THOUSAND OAKS, CA 91361 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 6/1/2021 | Partial Inspection | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 6/7/2021 | Partial Approval | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 6/23/2021 | Partial Approval | RAUL BARAJAS |
| Pre-Gunite | 7/28/2021 | Partial Inspection | RAUL BARAJAS |
| Pool Piping | 7/30/2021 | Partial Approval | RICHARD STEINBACH |
| Pre-Gunite | 7/30/2021 | Approved | RICHARD STEINBACH |
| Rough-Plumbing | 7/30/2021 | Partial Approval | RICHARD STEINBACH |
| Deck | 10/4/2021 | Approved | RAUL BARAJAS |
| Grounding or Bonding | 10/4/2021 | Approved | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 4/17/2023 | Approved | STUART CHAPMAN |
| Final | 4/17/2023 | Corrections Issued | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 4/17/2023 | SGSOV Not Ready | STUART CHAPMAN |
| Pool Equipment Noise Test | 4/27/2023 | Not Ready for Inspection | JUAN ESCOTO DELGADO |
| Pool Equipment Noise Test | 5/4/2023 | Approved | JUAN ESCOTO DELGADO |
| Final | 5/5/2023 | Conditional Approval | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 5/5/2023 | SGSOV Approved | STUART CHAPMAN |
| Final | 8/4/2023 | OK to Issue CofO | STUART CHAPMAN |