1280 N STONE CANYON ROAD 90077
Certificate Information: 1280 N STONE CANYON ROAD 90077
- Application / Permit
- 19047-20000-00710
- Plan Check / Job No.
- B19VN07051
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 47'2"X 24'8" SWIMMING POOL AND 10' DIAMATER SPA PER ENGINEER.
- Permit Issued
- Issued on 7/8/2019
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 2/26/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/30/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/30/2019 | PINANK PATEL |
| Corrections Issued | 5/1/2019 | PINANK PATEL |
| Building Plans Picked Up | 5/2/2019 | APPLICANT |
| Applicant returned to address corrections | 6/10/2019 | PINANK PATEL |
| Plan Check Approved | 7/8/2019 | PINANK PATEL |
| Issued | 7/8/2019 | LADBS |
| CofO in Progress | 2/19/2022 | CHRISTOPHER WILSON |
| CofO in Progress | 2/19/2022 | CHRISTOPHER WILSON |
| Permit Finaled | 2/26/2022 | DANIEL ORRANTE |
| CofO Issued | 2/26/2022 | DANIEL ORRANTE |
| Permit Finaled | 2/26/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/8/2019 | KRISTEN LY |
| Watercourse | Cleared | 5/8/2019 | KRISTEN LY |
| ZA Case | Cleared | 5/8/2019 | NOAH MCCOY |
| Grading Pre-Inspection | Cleared | 6/10/2019 | PINANK PATEL |
Contact Information
| Contractor | Holz Richard Inc; Lic. No.: 294504-B | 520 S SEPULVEDA BLVD #407 LOS ANGELES, CA 90049 |
| Engineer | Azizisefat,, Solayman; Lic. No.: C57840 | 19510 VENTURA BLVD STE 110 TARZANA, CA 91356 |
| Landscape Architect | Eriksson,, Nord Jon; Lic. No.: LA2858 | 844 E. GREEN STREET STE 201 PASADENA, CA 91101 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| FLOOD-Proofing Certificate | 8/16/2019 | Approved | CHRISTOPHER WILSON |
| Pre-Gunite | 8/16/2019 | Corrections Issued | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 8/19/2019 | Partial Approval | CHRISTOPHER WILSON |
| Final | 8/19/2019 | Partial Inspection | CHRISTOPHER WILSON |
| Grounding or Bonding | 8/19/2019 | Partial Approval | CHRISTOPHER WILSON |
| Pool Piping | 8/19/2019 | Approved | CHRISTOPHER WILSON |
| Pre-Gunite | 8/19/2019 | Approved | CHRISTOPHER WILSON |
| Rough-Electrical | 8/19/2019 | Partial Approval | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 9/24/2019 | Partial Approval | CARLOS MATAMOROS |
| Grounding or Bonding | 9/24/2019 | Approved | CARLOS MATAMOROS |
| Pre-Gunite | 9/24/2019 | Approved | CARLOS MATAMOROS |
| Rough-Plumbing | 9/24/2019 | Approved | CARLOS MATAMOROS |
| Deck | 12/12/2019 | Partial Approval | ANTHONY MCDOWALL |
| Enclosure/Fence | 10/7/2020 | Approved | CHRISTOPHER WILSON |
| Equipment Noise Level | 11/9/2020 | Approved | DA LIU |
| Excavation/Setback/Form/Re-Bar | 11/24/2020 | Approved | CHRISTOPHER WILSON |
| FLOOD-Elevation Certificate | 11/24/2020 | Approved | CHRISTOPHER WILSON |
| Final | 11/24/2020 | Corrections Issued | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 11/24/2020 | SGSOV Approved | CHRISTOPHER WILSON |
| Final | 12/10/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| Final | 1/6/2021 | Corrections Issued | CHRISTOPHER WILSON |
| Final | 4/26/2021 | Conditional Approval | CHRISTOPHER WILSON |
| Final | 9/22/2021 | Conditional Approval | CHRISTOPHER WILSON |
| Final | 12/28/2021 | Corrections Issued | CHRISTOPHER WILSON |
| Final | 1/19/2022 | OK to Issue CofO | CHRISTOPHER WILSON |