960 N LA BREA AVE 90038
Certificate Information: 960 N LA BREA AVE 90038
- Application / Permit
- 19047-20000-00434
- Plan Check / Job No.
- B19VN04199
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- Commercial
- Primary Use
- (4) Pool/Spa - Public
- Work Description
- NEW (18'-6"x 10'-0") SPA AT 4TH FLOOR. WORK PER ENGINEER.
- Permit Issued
- Issued on 7/21/2020
- Issuing Office
- Current Status
- CofO Issued on 12/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/15/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/11/2019 | TROY DEGUZMAN |
| Disabled Access Plans Picked Up | 4/15/2019 | APPLICANT |
| Corrections Issued | 4/16/2019 | TROY DEGUZMAN |
| Quality Review Completed | 4/19/2019 | STEVEN KIM |
| Building Plans Picked Up | 4/24/2019 | APPLICANT |
| Applicant returned to address corrections | 7/10/2020 | TROY DEGUZMAN |
| Plan Check Approved | 7/21/2020 | TROY DEGUZMAN |
| Issued | 7/21/2020 | APPLICANT |
| CofO in Progress | 12/5/2022 | TIMOTHY BUXTON |
| CofO Issued | 12/5/2022 | ERNESTO CORRAL |
| Permit Finaled | 12/5/2022 | ERNESTO CORRAL |
Permit Application Clearance Information
| "Q" conditions | Cleared | 10/3/2019 | DAISY BENICIA |
| CPC | Cleared | 10/3/2019 | DAISY BENICIA |
| ZA Case | Cleared | 10/3/2019 | DAISY BENICIA |
| ZA Case | Cleared | 10/3/2019 | DAISY BENICIA |
| DAS Clearance | Cleared | 6/12/2020 | TROY DEGUZMAN |
| Public Swimming Pool approval | Cleared | 7/9/2020 | LACDHS APPROVED |
Contact Information
| Contractor | Addison Pools Inc; Lic. No.: 753417-C53 | 4363 WOODMAN AVENUE SHERMAN OAKS, CA 91423 |
| Engineer | Zhang,, Yao; Lic. No.: C74572 | 538 ROCCO CIRCLE CORONA, CA 92882 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Pre-Stress Concrete | 2/9/2021 | Conditional Approval | TIMOTHY BUXTON |
| Enclosure/Fence | 3/22/2022 | Approved | TIMOTHY BUXTON |
| Excavation/Setback/Form/Re-Bar | 5/31/2022 | Approved | TIMOTHY BUXTON |
| Final | 5/31/2022 | Conditional Approval | TIMOTHY BUXTON |
| METHANE-Barrier | 5/31/2022 | Approved | TIMOTHY BUXTON |
| METHANE-Rough | 5/31/2022 | Approved | TIMOTHY BUXTON |
| METHANE-Subgrade | 5/31/2022 | Approved | TIMOTHY BUXTON |
| Pre-Gunite | 5/31/2022 | Approved | TIMOTHY BUXTON |
| SGSOV-Seismic Gas S/O Valve | 5/31/2022 | SGSOV Approved | TIMOTHY BUXTON |