3721 N MEADVILLE DR 91403

Certificate Information: 3721 N MEADVILLE DR 91403

Application / Permit
19047-20000-00050
Plan Check / Job No.
B19VN00556
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 37'-0" X 17'-0" SWIMMING POOL W/ 9'-0" X 9'-0" SPA PER ENGINEERING.
Permit Issued
Issued on 12/16/2019
Issuing Office
Valley
Current Status
CofO Issued on 7/1/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/14/2019 APPLICANT
Assigned to Plan Check Engineer 2/4/2019 ARTIN ZARUKIAN
Corrections Issued 2/6/2019 ARTIN ZARUKIAN
Quality Review Completed 2/11/2019 ABDUL CHEGENI
Building Plans Picked Up 2/12/2019 APPLICANT
Plan Check Approved 10/4/2019 ARTIN ZARUKIAN
Issued 12/16/2019 LADBS
CofO in Progress 7/1/2020 MICHAEL SMITH
CofO Issued 7/1/2020 MICHAEL SMITH
Permit Finaled 7/1/2020 MICHAEL SMITH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 9/24/2019 ALDO UBAU
Specific Plan Cleared 9/24/2019 LIZZI BEDUYA
ZI Cleared 9/24/2019 LIZZI BEDUYA
Miscellaneous Cleared 10/4/2019 ARTIN ZARUKIAN

Contact Information

Contractor Avanti Pools Inc; Lic. No.: 772516-C53 8138 ORION AVE      VAN NUYS, CA 91406
Engineer Biedenbach,, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807
Engineer Rana,, Masood Sarwar; Lic. No.: C70659 19560 SHADOW RIDGE WY      NORTHRIDGE, CA 91326
Geologist Putnam,, Lance Richard; Lic. No.: EG2469 6634 VALJEAN AVE      VAN NUYS, CA 91406

Inspector Information

DAVID ANDERSON, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI
RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Gas Piping or Gas Test 3/26/2020 Not Ready for Inspection DANIEL ORRANTE
Grounding or Bonding 3/26/2020 Approved DANIEL ORRANTE
Pool Piping 3/26/2020 Approved DANIEL ORRANTE
Pre-Gunite 3/26/2020 Approved DANIEL ORRANTE
Rough-Electrical 3/26/2020 Not Ready for Inspection DANIEL ORRANTE
Gas Piping or Gas Test 4/2/2020 Approved RONALD COWAN
Rough-Electrical 4/2/2020 Approved RONALD COWAN
Excavation/Setback/Form/Re-Bar 6/15/2020 Approved THOMAS FINNILA
Final 6/15/2020 Partial Inspection THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 6/15/2020 SGSOV Not Ready THOMAS FINNILA
Final 6/17/2020 OK to Issue CofO DANIEL DREW
SGSOV-Seismic Gas S/O Valve 6/17/2020 SGSOV Approved DANIEL DREW