15105 W WEDDINGTON ST 91411

Certificate Information: 15105 W WEDDINGTON ST 91411

Application / Permit
19047-20000-00008
Plan Check / Job No.
B19VN00079
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
New 11' X 32' pool with 8' X 9' attached spa per Std Plan #265
Permit Issued
Issued on 1/10/2019
Issuing Office
Valley
Current Status
CofO Issued on 1/27/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/3/2019 APPLICANT
Assigned to Plan Check Engineer 1/3/2019 BINH PHAN
Corrections Issued 1/3/2019 BINH PHAN
Applicant returned to address corrections 1/10/2019 ALDOUS CHIC
Applicant returned to address corrections 1/10/2019 ARTIN ZARUKIAN
Issued 1/10/2019 LADBS
CofO in Progress 12/1/2025 JACK KARGODORIAN
Permit Finaled 1/27/2026 RUBEN SALAS
CofO Issued 1/27/2026 RUBEN SALAS
Permit Finaled 1/27/2026 RUBEN SALAS

Permit Application Clearance Information

Miscellaneous Cleared 1/10/2019 HERMINIGILDO AGUSTIN
Miscellaneous Cleared 1/10/2019 HERMINIGILDO AGUSTIN
ZA Case Cleared 1/10/2019 RICK TORRES
ZA Case Cleared 1/10/2019 RICK TORRES

Contact Information

Contractor Owner-Builder       ,
Engineer Zhang,, Yao; Lic. No.: C74572 538 ROCCO CIRCLE      CORONA, CA 92882

Inspector Information

DAVID ANDERSON, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI
RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/24/2019 No Access for Inspection CHRISTOPHE COCHRAN
Pre-Gunite 9/24/2019 No Access for Inspection CHRISTOPHE COCHRAN
Rough-Plumbing 9/24/2019 No Access for Inspection CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 11/7/2019 Approved DANIEL ORRANTE
Pre-Gunite 11/7/2019 Approved DANIEL ORRANTE
Rough-Plumbing 11/7/2019 Approved DANIEL ORRANTE
Deputy Shotcrete 12/9/2019 Conditional Approval CHRISTOPHE COCHRAN
Pre-Inspection 4/13/2023 Partial Inspection ARAM AVEDISIAN
Rough-Electrical 4/25/2023 Not Ready for Inspection THOMAS FINNILA
Rough-Plumbing 4/25/2023 Not Ready for Inspection THOMAS FINNILA
Deck 12/11/2024 Corrections Issued JACK KARGODORIAN
Gas Piping or Gas Test 12/11/2024 Approved JACK KARGODORIAN
Rough-Electrical 12/11/2024 Approved JACK KARGODORIAN
Rough-Plumbing 12/11/2024 Approved JACK KARGODORIAN
Enclosure/Fence 9/5/2025 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 9/5/2025 SGSOV Approved JACK KARGODORIAN
Final 10/8/2025 Corrections Issued JACK KARGODORIAN
Final 10/15/2025 OK to Issue CofO JACK KARGODORIAN