715 N EL ATAJO ST 90065
Certificate Information: 715 N EL ATAJO ST 90065
- Application / Permit
- 19047-10000-02051
- Plan Check / Job No.
- B19LA25545
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW SWIMMING POOL AND SPA PER CITY STANDARD PLAN # 268 1 OF 3
- Permit Issued
- Issued on 2/10/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/31/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/3/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/2/2020 | ZAW HAN |
| Corrections Issued | 1/8/2020 | ZAW HAN |
| Quality Review Completed | 1/17/2020 | HERNAN ARREOLA |
| Building Plans Picked Up | 1/22/2020 | APPLICANT |
| Plan Check Approved | 2/10/2020 | ZAW HAN |
| Issued | 2/10/2020 | LADBS |
| CofO in Progress | 7/21/2020 | OSVALDO PARAMO |
| Permit Finaled | 7/31/2020 | DEROLD HAUFF |
| CofO Issued | 7/31/2020 | DEROLD HAUFF |
| Permit Finaled | 7/31/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/6/2020 | ERIK BEASLEY |
| Sewer availability | Cleared | 2/6/2020 | ERIK BEASLEY |
| Specific Plan | Cleared | 2/6/2020 | RICHARD REASER |
| ZA Case | Cleared | 2/6/2020 | RICHARD REASER |
| Grading Pre-Inspection | Cleared | 2/10/2020 | TODD MALAND |
Contact Information
| Contractor | Blue Fountain Pools And Spas Inc; Lic. No.: 1004554-C53 | 1151 S GRAND AVE GLENDORA, CA 91740 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Piping or Gas Test | 3/20/2020 | Partial Approval | OSVALDO PARAMO |
| Pre-Gunite | 3/20/2020 | Approved | OSVALDO PARAMO |
| Rough-Electrical | 3/20/2020 | Partial Approval | OSVALDO PARAMO |
| Deck | 4/30/2020 | Approved | OSVALDO PARAMO |
| Enclosure/Fence | 5/26/2020 | Partial Inspection | OSVALDO PARAMO |
| Enclosure/Fence | 5/29/2020 | Approved | OSVALDO PARAMO |
| Pool Equipment Noise Test | 7/13/2020 | Approved | ROBERT CHAVEZ |
| Excavation/Setback/Form/Re-Bar | 7/14/2020 | Approved | OSVALDO PARAMO |
| Final | 7/14/2020 | OK to Issue CofO | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 7/14/2020 | SGSOV Approved | OSVALDO PARAMO |