8470 W FRANKLIN AVE 90069
Certificate Information: 8470 W FRANKLIN AVE 90069
- Application / Permit
- 19047-10000-02028
- Plan Check / Job No.
- B19LA25358
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- FOR (N) POOL + SPA
- Permit Issued
- Issued on 8/3/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/2/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/19/2019 | CATHERINE CHEN |
| Green Plans Picked Up | 1/27/2020 | APPLICANT |
| Corrections Issued | 1/29/2020 | CATHERINE CHEN |
| Quality Review Completed | 2/3/2020 | MINYE PAK |
| Building Plans Picked Up | 2/10/2020 | APPLICANT |
| Applicant returned to address corrections | 10/2/2020 | CATHERINE CHEN |
| Applicant returned to address corrections | 10/30/2020 | CATHERINE CHEN |
| Applicant returned to address corrections | 11/2/2020 | CATHERINE CHEN |
| Applicant returned to address corrections | 2/8/2021 | CATHERINE CHEN |
| Applicant returned to address corrections | 2/18/2021 | CATHERINE CHEN |
| Applicant returned to address corrections | 2/22/2021 | CATHERINE CHEN |
| Applicant returned to address corrections | 12/10/2021 | CATHERINE CHEN |
| Applicant returned to address corrections | 12/15/2021 | CATHERINE CHEN |
| Applicant returned to address corrections | 12/17/2021 | CATHERINE CHEN |
| Applicant returned to address corrections | 12/27/2021 | CATHERINE CHEN |
| Applicant returned to address corrections | 12/28/2021 | CATHERINE CHEN |
| Applicant returned to address corrections | 1/25/2022 | CATHERINE CHEN |
| Plan Check Approved | 5/18/2022 | SINA KHOSRAVI |
| Issued | 8/3/2022 | APPLICANT |
| CofO in Progress | 8/27/2025 | ROY SPAULDING |
| No Progress | 9/2/2025 | DEROLD HAUFF |
| CofO in Progress | 9/2/2025 | DEROLD HAUFF |
| Permit Finaled | 9/4/2025 | DEROLD HAUFF |
| CofO Issued | 9/4/2025 | DEROLD HAUFF |
| Permit Finaled | 9/4/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/19/2020 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 2/19/2020 | MARKOS PEREZ-BRAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 25531 PRADO DELAS BELLOTAS CALABASAS, CA 91302 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Other (see comments) | 12/15/2022 | Conditional Approval | STUART CHAPMAN |
| Piling/Pier/Caisson | 1/24/2023 | Partial Approval | STUART CHAPMAN |
| Pre-Gunite | 7/17/2023 | Approved | RAUL BARAJAS |
| Deputy Shotcrete | 8/1/2023 | Conditional Approval | STUART CHAPMAN |
| Enclosure/Fence | 3/27/2025 | Not Ready for Inspection | ROY SPAULDING |
| Enclosure/Fence | 3/28/2025 | Approved | ROY SPAULDING |
| Excavation/Setback/Form/Re-Bar | 4/16/2025 | Approved | ROY SPAULDING |
| Final | 4/16/2025 | Not Ready for Inspection | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 4/16/2025 | SGSOV Approved | ROY SPAULDING |
| Final | 8/26/2025 | OK to Issue CofO | ROY SPAULDING |