2109 N REDROCK CT 90039
Certificate Information: 2109 N REDROCK CT 90039
- Application / Permit
- 19047-10000-01926
- Plan Check / Job No.
- B19LA24110
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW POOL
- Permit Issued
- Issued on 3/26/2021
- Issuing Office
- Current Status
- CofO Issued on 11/17/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/12/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2019 | ALBERT SERVIN |
| Corrections Issued | 11/26/2019 | ALBERT SERVIN |
| Quality Review Completed | 11/27/2019 | KEN GILL |
| Building Plans Picked Up | 12/4/2019 | APPLICANT |
| Plan Check Approved | 1/31/2020 | ALBERT SERVIN |
| Issued | 3/26/2021 | APPLICANT |
| CofO in Progress | 10/24/2022 | JOSEPH MCGARRY |
| Permit Finaled | 11/17/2022 | DEROLD HAUFF |
| CofO Issued | 11/17/2022 | DEROLD HAUFF |
| Permit Finaled | 11/17/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/22/2020 | JUAN ASHTON |
| Low Impact Development | Cleared | 1/22/2020 | SARAH YOUSSEF |
| Sewer availability | Cleared | 1/22/2020 | JUAN ASHTON |
Contact Information
| Contractor | Blue Square Construction; Lic. No.: 816712-B | 3740 SUMMERSHORE LN WESTLAKE VILLAGE, CA 91361 |
| Engineer | Kim,, Seung Su; Lic. No.: S5909 | 15808 APOLLO PLACE GARDENA, CA 90249 |
| Geologist | Miller,, Jonathan Steven; Lic. No.: EG2391 | 1423 S BEVERLY GLEN BLVD APT B LOS ANGELES, CA 90024 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/26/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 9/8/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Gas Piping or Gas Test | 9/23/2021 | Partial Approval | JOSEPH MCGARRY |
| Pool Piping | 9/23/2021 | Partial Approval | JOSEPH MCGARRY |
| Pre-Gunite | 9/23/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Grounding or Bonding | 11/9/2021 | Partial Approval | JOSEPH MCGARRY |
| Pre-Gunite | 11/9/2021 | Approved | JOSEPH MCGARRY |
| Rough-Electrical | 11/9/2021 | Partial Approval | JOSEPH MCGARRY |
| Special/Order Compliance | 4/1/2022 | Partial Approval | JOSEPH MCGARRY |
| Gas Piping or Gas Test | 4/27/2022 | Approved | JOSEPH MCGARRY |
| Pool Piping | 4/27/2022 | Approved | JOSEPH MCGARRY |
| Deck | 5/16/2022 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Final | 6/27/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| Enclosure/Fence | 7/7/2022 | Conditional Approval | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 9/14/2022 | Approved | JOSEPH MCGARRY |
| Final | 9/14/2022 | Corrections Issued | JOSEPH MCGARRY |
| Pool Equipment Noise Test | 9/14/2022 | Approved | ZEYDI STEWART |
| Pool/Spa Cover | 9/14/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 9/14/2022 | SGSOV Approved | JOSEPH MCGARRY |
| Grading Pre-Inspection | 9/29/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| Pre-Inspection | 9/29/2022 | Approved | JOSEPH MCGARRY |
| Final | 10/5/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| Final | 10/19/2022 | OK to Issue CofO | JOSEPH MCGARRY |