825 N ALMA REAL DR 90272

Certificate Information: 825 N ALMA REAL DR 90272

Application / Permit
19047-10000-01910
Plan Check / Job No.
B19LA23913
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
1) NEW POOL 27' X 14' & SPA 7' X 7'
Permit Issued
Issued on 11/8/2019
Issuing Office
Metro
Current Status
CofO Issued on 12/13/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/8/2019 APPLICANT
Assigned to Plan Check Engineer 11/8/2019 FARSHAD ALIMOHAMADI
Plan Check Approved 11/8/2019 FARSHAD ALIMOHAMADI
Issued 11/8/2019 LADBS
CofO in Progress 10/21/2021 ANDREW NAVE
Permit Finaled 12/13/2021 DANIEL ORRANTE
CofO Issued 12/13/2021 DANIEL ORRANTE
Permit Finaled 12/13/2021 DANIEL ORRANTE

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Horusicky Construction Inc; Lic. No.: 309844-C53 P O BOX 3789      PALOS VERDES, CA 90274
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

STEPHANIE SWANSON, (213) 469-1255 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 4/13/2020 Not Ready for Inspection ANDREW NAVE
Pool Piping 5/6/2020 Approved GERMAN RODRIGUEZ MENDOZA
Pre-Gunite 5/6/2020 Approved GERMAN RODRIGUEZ MENDOZA
Deck 7/16/2020 Approved ANDREW NAVE
Enclosure/Fence 10/23/2020 Approved ANDREW NAVE
Final 9/30/2021 Corrections Issued ANDREW NAVE
SGSOV-Seismic Gas S/O Valve 9/30/2021 SGSOV Approved ANDREW NAVE
Final 10/14/2021 Partial Inspection ANDREW NAVE
Pool Equipment Noise Test 10/18/2021 Approved JAMES VORHIS
Final 10/21/2021 OK to Issue CofO ANDREW NAVE