21110 W OXNARD ST 91367

Certificate Information: 21110 W OXNARD ST 91367

Application / Permit
19047-10000-01862
Plan Check / Job No.
B19LA23293
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
Commercial
Primary Use
(4) Pool/Spa - Public
Work Description
NEW POOL, (PUBLIC) ON GRADE(1st-FL) OF NEW 7 STORY HOTEL, WITH ONE LEVEL BASEMENT (170 GUESTROOMS). SEE PER#18010-10000-02438.
Permit Issued
Issued on 10/5/2020
Issuing Office
Current Status
Permit Finaled on 3/24/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/1/2019 APPLICANT
Assigned to Plan Check Engineer 11/21/2019 VU NGUYEN
Corrections Issued 11/27/2019 VU NGUYEN
Quality Review Completed 12/4/2019 LAWRENCE QUIRANTE
Building Plans Picked Up 12/9/2019 APPLICANT
Applicant returned to address corrections 2/28/2020 VU NGUYEN
Disabled Access Plans Picked Up 2/28/2020 APPLICANT
Plan Check Approved 10/1/2020 VU NGUYEN
Issued 10/5/2020 APPLICANT
Permit Finaled 3/24/2022 CAMERON CHABAN

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/28/2020 ERIK BEASLEY
Miscellaneous Cleared 2/28/2020 SARAHI ORTEGA
Miscellaneous Cleared 2/28/2020 SARAHI ORTEGA
Sewer availability Cleared 2/28/2020 ERIK BEASLEY
Specific Plan Cleared 2/28/2020 SARAHI ORTEGA
DAS Clearance Cleared 9/9/2020 EDDIE GARIN
Public Swimming Pool approval Cleared 10/1/2020 LACDHS APPROVED

Contact Information

Architect Nichols,, Robert B; Lic. No.: C29164 P O BOX 55384      VALENCIA, CA 91385
Contractor Ebco General Contractor Lp; Lic. No.: 1030694-B 305 W GILLIS AVENUE      CAMERON, TX 76520
Engineer Biddulph,, Sandra; Lic. No.: S4225 7488 PASEO CRISTAL      CARLSBAD, CA 92009
Engineer Chapman,, Ryan Scott; Lic. No.: C86076 N95W29130 FAWN CT      COLGATE, WI 53017
Engineer Jordan,, Ricardo; Lic. No.: C68436 1050 ISLAND AVE UNIT 109      SAN DIEGO, CA 92101

Inspector Information

BRIAN KELLY, (818) 374-1127 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/14/2020 Approved HAMID PISHEHVAR
Grounding or Bonding 12/14/2020 Approved HAMID PISHEHVAR
Pool Piping 12/14/2020 Partial Inspection HAMID PISHEHVAR
Pre-Gunite 12/14/2020 Approved HAMID PISHEHVAR
Rough-Plumbing 12/14/2020 Partial Inspection HAMID PISHEHVAR
Grounding or Bonding 7/30/2021 No Access for Inspection DANIEL VARNUM
Deck 8/3/2021 Not Ready for Inspection PAUL DAVIDSON
Grounding or Bonding 8/3/2021 Not Ready for Inspection PAUL DAVIDSON
Rough-Electrical 8/3/2021 Not Ready for Inspection PAUL DAVIDSON
Enclosure/Fence 11/9/2021 Not Ready for Inspection DANIEL VARNUM
Final 2/9/2022 Partial Inspection CAMERON CHABAN
SGSOV-Seismic Gas S/O Valve 2/9/2022 SGSOV Not Ready CAMERON CHABAN
Final 3/24/2022 Permit Finaled CAMERON CHABAN
SGSOV-Seismic Gas S/O Valve 3/24/2022 SGSOV Approved CAMERON CHABAN