4084 W LEEWARD AVE 90005

Certificate Information: 4084 W LEEWARD AVE 90005

Application / Permit
19047-10000-00974
Plan Check / Job No.
B19LA11790
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 33' X 13' SWIMMING POOL AND 5.5' X 6.5 SPA.
Permit Issued
Issued on 5/5/2021
Issuing Office
Current Status
CofO Issued on 1/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/7/2019 APPLICANT
Green Plans Picked Up 6/25/2019 APPLICANT
Assigned to Plan Check Engineer 6/27/2019 SERGIO GUTIERREZ
Corrections Issued 7/2/2019 SERGIO GUTIERREZ
Quality Review Completed 7/17/2019 KESETE HAREGOT
Building Plans Picked Up 7/19/2019 APPLICANT
Applicant returned to address corrections 9/5/2019 SERGIO GUTIERREZ
Applicant returned to address corrections 10/21/2019 SERGIO GUTIERREZ
Plan Check Approved 2/26/2020 SERGIO GUTIERREZ
Issued 5/5/2021 APPLICANT
CofO in Progress 12/7/2024 JEFFREY MEAD
Permit Finaled 1/15/2025 DEROLD HAUFF
CofO Issued 1/15/2025 DEROLD HAUFF
Permit Finaled 1/15/2025 DEROLD HAUFF

Permit Application Clearance Information

Specific Plan Cleared 10/22/2019 RUBEN VASQUEZ
HPOZ Cleared 2/19/2020 AMANDA KAINER
Miscellaneous Cleared 2/19/2020 AMANDA KAINER
ZI Cleared 2/19/2020 AMANDA KAINER
Excavation more than 5-ft deep Cleared 2/26/2020 CALOSHA APPROVED

Contact Information

Architect Banyasz,, Bojana; Lic. No.: C32926 3910 TAMPICO AVENUE      LOS ANGELES, CA 90032
Contractor Onmark Builders; Lic. No.: 1061309-B 5907 RHODES AVE      VALLEY VILLAGE, CA 91607
Engineer Kim,, Seung Su; Lic. No.: S5909 15808 APOLLO PLACE      GARDENA, CA 90249

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Equipment Noise Level 10/1/2024 Approved ANDEY CHAPARRO
Pool Equipment Noise Test 10/1/2024 Approved ANDEY CHAPARRO
Final 10/2/2024 Not Ready for Inspection RONNIE MINDANAO
SGSOV-Seismic Gas S/O Valve 10/2/2024 SGSOV Not Ready RONNIE MINDANAO
Final 11/14/2024 Corrections Issued JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 11/14/2024 SGSOV Not Ready JEFFREY MEAD
Final 12/4/2024 Corrections Issued JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 12/4/2024 SGSOV Not Ready JEFFREY MEAD
Final 12/6/2024 OK to Issue CofO JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 12/6/2024 SGSOV Approved JEFFREY MEAD