4176 N GREENBUSH AVE 91423
Certificate Information: 4176 N GREENBUSH AVE 91423
- Application / Permit
- 19047-10000-00771
- Plan Check / Job No.
- B19LA09523
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 26'X 12'X 5'-8" FIBERGLASS SWIMMING POOL
- Permit Issued
- Issued on 10/17/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/27/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/9/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/13/2019 | VU NGUYEN |
| Corrections Issued | 6/20/2019 | VU NGUYEN |
| Quality Review Completed | 6/20/2019 | MICHAEL PEREZ |
| Building Plans Picked Up | 9/13/2019 | APPLICANT |
| Plan Check Approved | 10/17/2019 | VU NGUYEN |
| Issued | 10/17/2019 | LADBS |
| CofO in Progress | 2/9/2021 | CHARLES POWELL |
| CofO Issued | 3/27/2021 | MICHAEL SMITH |
| Permit Finaled | 3/27/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 10/17/2019 | OSCAR CASTRO |
| Grading Pre-Inspection | Cleared | 10/17/2019 | VU NGUYEN |
Contact Information
| Contractor | Ray'S Pool & Spa; Lic. No.: 492991-C53 | 6924 BASSWOOD PLACE RANCHO CUCAMONGA, CA 91739 |
| Engineer | Poindexter,, Donald Robert; Lic. No.: C24420 | 2835 BOWEN ST GRATON, CA 95444 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Rough-Electrical | 2/10/2020 | Approved | CHARLES POWELL |
| Rough-Plumbing | 2/10/2020 | Approved | CHARLES POWELL |
| Deck | 2/26/2020 | Approved | CHARLES POWELL |
| Grounding or Bonding | 2/26/2020 | Approved | CHARLES POWELL |
| Final | 5/4/2020 | Corrections Issued | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 5/4/2020 | SGSOV Not Ready | THOMAS FINNILA |
| Final | 10/5/2020 | Corrections Issued | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 10/5/2020 | SGSOV Not Ready | ARAM AVEDISIAN |
| Pool Equipment Noise Test | 10/14/2020 | Approved | FELIPE PENICHE |
| Final | 10/27/2020 | Not Ready for Inspection | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 10/27/2020 | SGSOV Approved | ARAM AVEDISIAN |
| Final | 2/9/2021 | OK to Issue CofO | CHARLES POWELL |