4938 S IMLAY AVE 90230
Certificate Information: 4938 S IMLAY AVE 90230
- Application / Permit
- 19047-10000-00368
- Plan Check / Job No.
- B19LA04573
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW POOL (7'-0" X 20'-0")
- Permit Issued
- Issued on 5/22/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/26/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/6/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 3/28/2019 | EMMANUEL MARTINEZ |
| Corrections Issued | 4/4/2019 | EMMANUEL MARTINEZ |
| Quality Review Completed | 4/8/2019 | JOSE RODRIGUEZ |
| Building Plans Picked Up | 4/17/2019 | APPLICANT |
| Applicant returned to address corrections | 5/6/2019 | EMMANUEL MARTINEZ |
| Plan Check Approved | 2/26/2020 | EMMANUEL MARTINEZ |
| Issued | 5/22/2020 | LADBS |
| CofO in Progress | 1/13/2022 | EVAN COOPER |
| Permit Finaled | 1/26/2022 | KENNETH NAGLE |
| CofO Issued | 1/26/2022 | KENNETH NAGLE |
| Permit Finaled | 1/26/2022 | KENNETH NAGLE |
Permit Application Clearance Information
| Construction within easement | Cleared | 2/26/2020 | WALTER RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/26/2020 | THOMAS LANG |
| Sewer availability | Cleared | 2/26/2020 | THOMAS LANG |
Contact Information
| Contractor | Treeium Inc; Lic. No.: 617148-B | 5352 LAUREL CANYON BLVD #200 VALLEY VILLAGE, CA 91607 |
| Engineer | Chiu,, Ivan Wai-Kuen; Lic. No.: C44672 | 2160 PARNELL WY ALTADENA, CA 91001 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/22/2021 | Approved | ENRIQUE MIRELES |
| Rough-Plumbing | 2/22/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Deck | 6/10/2021 | Approved | ENRIQUE MIRELES |
| Enclosure/Fence | 8/5/2021 | Approved | ENRIQUE MIRELES |
| Final | 8/23/2021 | Corrections Issued | JUAN VALENZUELA |
| Pre-Gunite | 8/23/2021 | Approved | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 8/23/2021 | SGSOV Not Ready | JUAN VALENZUELA |
| ELECTRICAL-Final | 12/2/2021 | Approved | ENRIQUE MIRELES |
| Final | 12/2/2021 | Corrections Issued | ENRIQUE MIRELES |
| PLUMBING-Final | 12/2/2021 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 12/2/2021 | SGSOV Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 12/21/2021 | Not Ready for Inspection | DAVID FEILER |
| Final | 12/21/2021 | Corrections Issued | DAVID FEILER |
| PLUMBING-Final | 12/21/2021 | Not Ready for Inspection | DAVID FEILER |
| Equipment Noise Level | 12/28/2021 | Approved | AGUSTIN ALVAREZMORALES |
| ELECTRICAL-Final | 1/3/2022 | Approved | EVAN COOPER |
| Final | 1/3/2022 | Corrections Issued | EVAN COOPER |
| PLUMBING-Final | 1/3/2022 | Approved | EVAN COOPER |
| Final | 1/13/2022 | OK to Issue CofO | EVAN COOPER |