1325 S THAYER AVE 90024

Certificate Information: 1325 S THAYER AVE 90024

Application / Permit
19030-30000-08651
Plan Check / Job No.
B19WL07399
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
Grading for new dwelling and site retaining wall.
Permit Issued
Issued on 5/17/2022
Issuing Office
Current Status
Permit Finaled on 2/9/2026

Permit Application Status History

Submitted 12/31/2019 APPLICANT
Assigned to Plan Check Engineer 1/30/2020 KAMRAN GHOTBI RAVANDI
Corrections Issued 2/3/2020 KAMRAN GHOTBI RAVANDI
Green Plans Picked Up 2/6/2020 APPLICANT
Quality Review Completed 2/11/2020 FELIX FIGUEROA
Applicant returned to address corrections 9/10/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 9/11/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 10/15/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 11/30/2020 KAMRAN GHOTBI RAVANDI
Plan Check Approved 3/25/2021 KAMRAN GHOTBI RAVANDI
Issued 5/17/2022 APPLICANT
Building Plans Picked Up 5/18/2022 APPLICANT
Permit Finaled 2/6/2026 JOHNNY MIRANDA

Permit Application Clearance Information

Construction near power lines Cleared 5/13/2020 WALTER RAMIREZ
Excavation more than 5-ft deep Cleared 11/30/2020 CALOSHA APPROVED

Contact Information

Contractor Ponderosa Pines Gen Contractors; Lic. No.: 450947-B 9616 RIESHEL STREET      PICO RIVERA, CA 90660
Engineer Salehipour,, Sassan A; Lic. No.: GE2579 1290 N LAKE AVENUE #204      PASADENA, CA 91104
Engineer Yadegari,, Shahriar; Lic. No.: C64591 267 S SAN PEDRO ST 124      LOS ANGELES, CA 90012

Inspector Information

JOHNNY MIRANDA, (310) 914-3937 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 4/8/2024 No Access for Inspection AL GAMBLE
Initial Grading 4/26/2024 Approved MATTHEW JENKINS
Rough 5/24/2024 Not Ready for Inspection MATTHEW JENKINS
Fill/Backfill 10/22/2024 Partial Inspection MATTHEW JENKINS
Sub-Drain 10/22/2024 Partial Approval MATTHEW JENKINS
Approved Compaction Report 12/4/2024 Partial Inspection MATTHEW JENKINS
Fill/Backfill 12/4/2024 Partial Inspection MATTHEW JENKINS
Excavation 4/3/2025 Partial Approval JOHNNY MIRANDA
Bottom/Toe 7/15/2025 Partial Approval AL GAMBLE
Bottom/Toe 8/22/2025 Not Ready for Inspection AL GAMBLE
Drainage Devices/Catch Basin 10/2/2025 Partial Approval AL GAMBLE
Sub-Drain 10/2/2025 Partial Approval AL GAMBLE
Approved Compaction Report 10/28/2025 Approved LANNY MERRICK
Bottom/Toe 12/8/2025 Not Ready for Inspection JOHNNY MIRANDA
Rough 12/8/2025 Not Ready for Inspection JOHNNY MIRANDA
Bottom/Toe 2/6/2026 Approved JOHNNY MIRANDA
Final 2/6/2026 Permit Finaled JOHNNY MIRANDA