869 N TOYOPA DR 90272
Certificate Information: 869 N TOYOPA DR 90272
- Application / Permit
- 19030-30000-08554
- Plan Check / Job No.
- B19WL07313
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- Removal & recompacion for (n) SFD.
- Permit Issued
- Issued on 3/26/2021
- Issuing Office
- Current Status
- Permit Finaled on 5/16/2023
Permit Application Status History
| Submitted | 12/27/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/3/2020 | MANUEL GARCIA |
| Plans on Hold | 2/3/2020 | KAMRAN GHOTBI RAVANDI |
| Hold Released | 5/18/2020 | KAMRAN GHOTBI RAVANDI |
| Corrections Issued | 6/12/2020 | MANUEL GARCIA |
| Quality Review Completed | 6/19/2020 | KAMRAN GHOTBI RAVANDI |
| Green Plans Picked Up | 6/23/2020 | APPLICANT |
| Applicant returned to address corrections | 8/28/2020 | MANUEL GARCIA |
| Applicant returned to address corrections | 9/1/2020 | MANUEL GARCIA |
| Applicant returned to address corrections | 11/15/2020 | MANUEL GARCIA |
| Applicant returned to address corrections | 1/13/2021 | MANUEL GARCIA |
| Applicant returned to address corrections | 3/3/2021 | MANUEL GARCIA |
| Building Plans Picked Up | 3/3/2021 | APPLICANT |
| Applicant returned to address corrections | 3/12/2021 | MANUEL GARCIA |
| Plan Check Approved | 3/19/2021 | MANUEL GARCIA |
| Plan Check Approved | 3/19/2021 | DAISY GUILLEN |
| Issued | 3/26/2021 | APPLICANT |
| Permit Finaled | 5/10/2023 | RUSSELL BONVOULOIR |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/18/2021 | MANUEL GARCIA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 21500 WYANDOTTE ST 106 CANOGA PARK, CA 91303 |
Inspector Information
| RUSSELL BONVOULOIR, (310) 914-3899 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 4/5/2021 | Approved | MATTHEW JENKINS |
| Sub-Drain | 5/14/2021 | Partial Approval | MATTHEW JENKINS |
| Sub-Drain | 6/15/2021 | Partial Approval | MATTHEW JENKINS |
| Approved Compaction Report | 7/20/2022 | Approved | TIMOTHY POWELL |
| Bottom/Toe | 5/10/2023 | Approved | RUSSELL BONVOULOIR |
| Final | 5/10/2023 | Permit Finaled | RUSSELL BONVOULOIR |
| Rough | 5/10/2023 | Approved | RUSSELL BONVOULOIR |