838 N BROOKTREE ROAD 90272

Certificate Information: 838 N BROOKTREE ROAD 90272

Application / Permit
19030-30000-08441
Plan Check / Job No.
B19WL07241
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
GRADING FOR (N) SFD, RETAIN. WALL, & POOL
Permit Issued
Issued on 5/23/2022
Issuing Office
Current Status
Permit Finaled on 9/9/2025

Permit Application Status History

Submitted 12/24/2019 APPLICANT
Assigned to Plan Check Engineer 2/13/2020 VLADIMIR ARUTYUNYAN
Corrections Issued 2/20/2020 VLADIMIR ARUTYUNYAN
Quality Review Completed 2/28/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 9/8/2020 VLADIMIR ARUTYUNYAN
Building Plans Picked Up 9/15/2020 APPLICANT
Green Plans Picked Up 6/9/2021 APPLICANT
Plan Check Approved 10/14/2021 VLADIMIR ARUTYUNYAN
Issued 5/23/2022 APPLICANT
Permit Finaled 9/8/2025 JOHNNY MIRANDA

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor N W G C Inc; Lic. No.: 770243-B 171 PIER AVENUE # 117      SANTA MONICA, CA 90405

Inspector Information

RUSSELL BONVOULOIR, (310) 914-3899 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 6/1/2022 Approved TIMOTHY POWELL
Bottom/Toe 6/14/2022 Partial Approval TIMOTHY POWELL
Bottom/Toe 6/14/2022 Partial Inspection MICHAEL TEMPLE
Excavation 6/16/2022 Partial Inspection TIMOTHY POWELL
Bottom/Toe 7/12/2022 Partial Approval TIMOTHY POWELL
Sub-Drain 12/30/2022 Partial Approval RUSSELL BONVOULOIR
Sub-Drain 2/2/2023 Partial Approval RUSSELL BONVOULOIR
Sub-Drain 2/14/2023 Partial Approval RUSSELL BONVOULOIR
Sub-Drain 4/13/2023 Partial Approval RUSSELL BONVOULOIR
Sub-Drain 9/29/2023 Partial Approval JOHNNY MIRANDA
Deputy Wood Construction 10/13/2023 Partial Approval JOHNNY MIRANDA
Sub-Drain 10/13/2023 Partial Approval JOHNNY MIRANDA
Sub-Drain 11/14/2023 Partial Approval JOHNNY MIRANDA
Approved Compaction Report 3/25/2025 Corrections Issued MATTHEW JENKINS
Bottom/Toe 3/25/2025 Approved JOHNNY MIRANDA
FLOOD-Proofing Certificate 3/25/2025 Approved JOHNNY MIRANDA
Final 3/25/2025 Corrections Issued JOHNNY MIRANDA
Rough 3/25/2025 Approved JOHNNY MIRANDA
Drainage Devices/Catch Basin 7/3/2025 Partial Approval JOHNNY MIRANDA
Sub-Drain 7/3/2025 Partial Approval JOHNNY MIRANDA
Approved Compaction Report 7/10/2025 Approved MATTHEW JENKINS
Final 9/8/2025 Permit Finaled JOHNNY MIRANDA