4406 N FULTON AVE 91423
Certificate Information: 4406 N FULTON AVE 91423
- Application / Permit
- 19030-30000-07279
- Plan Check / Job No.
- B19WL06287
- Group
- Building
- Type
- Grading
- Sub-Type
- Apartment
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- Grading for new apartment building
- Permit Issued
- Issued on 10/8/2021
- Issuing Office
- Current Status
- Permit Finaled on 7/15/2024
Permit Application Status History
| Submitted | 11/8/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/5/2019 | MARJAN SHENASI |
| Corrections Issued | 12/26/2019 | MARJAN SHENASI |
| Disabled Access Plans Picked Up | 12/26/2019 | APPLICANT |
| Quality Review Completed | 1/10/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 6/22/2020 | MARJAN SHENASI |
| Applicant returned to address corrections | 9/1/2020 | MARJAN SHENASI |
| Green Plans Picked Up | 9/1/2020 | APPLICANT |
| Applicant returned to address corrections | 9/28/2020 | MARJAN SHENASI |
| Applicant returned to address corrections | 11/5/2020 | MARJAN SHENASI |
| Building Plans Picked Up | 12/17/2020 | APPLICANT |
| Applicant returned to address corrections | 2/16/2021 | MARJAN SHENASI |
| Applicant returned to address corrections | 2/23/2021 | MARJAN SHENASI |
| Applicant returned to address corrections | 3/10/2021 | MARJAN SHENASI |
| Applicant returned to address corrections | 6/18/2021 | MARJAN SHENASI |
| Applicant returned to address corrections | 9/7/2021 | MARJAN SHENASI |
| Applicant returned to address corrections | 9/20/2021 | MARJAN SHENASI |
| Applicant returned to address corrections | 10/4/2021 | MARJAN SHENASI |
| Plan Check Approved | 10/6/2021 | MARJAN SHENASI |
| Issued | 10/8/2021 | APPLICANT |
| Permit Finaled | 7/15/2024 | MANUEL TEJADA |
Permit Application Clearance Information
| Construction near power lines | Cleared | 5/22/2020 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 5/28/2020 | JOHN LIN |
| Excavation more than 5-ft deep | Cleared | 11/18/2020 | CALOSHA APPROVED |
| Miscellaneous | Cleared | 1/27/2021 | MIGUEL GAMBOA |
| ZI | Cleared | 1/27/2021 | MIGUEL GAMBOA |
| Work Adjacent to Public Way | Cleared | 8/30/2021 | LEE GUILBEAUX |
Contact Information
| Architect | Kostic,, Vasa; Lic. No.: C10740 | 1827-10TH ST_#4 SANTA MONICA, CA 90404 |
| Contractor | Summerland Partners Inc; Lic. No.: 865002-B | 23622 CALABASAS ROAD SUITE 121 CALABASAS, CA 91302 |
| Engineer | Azarbin,, Hamid; Lic. No.: C64515 | 22655 COVELLO ST WEST HILLS, CA 91307 |
| Engineer | Babayan,, Raffi Samuel; Lic. No.: C72168 | 7718 DAY STREET LOS ANGELES, CA 91042 |
| Engineer | Dejban,, Masoud; Lic. No.: S2521 | 17200 VENTURA BLVD STE 213A ENCINO, CA 91316 |
Inspector Information
| MATTHEW JENKINS, (818) 374-4357 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 10/28/2021 | Approved | TIMOTHY POWELL |
| Deputy Grading | 11/12/2021 | Approved | TIMOTHY POWELL |
| Deputy Grading | 12/8/2021 | Approved | TIMOTHY POWELL |
| Deputy Grading | 12/13/2021 | Approved | TIMOTHY POWELL |
| Deputy Grading | 12/16/2021 | Approved | ALEXANDER ANDREWS |
| Sub-Drain | 12/29/2021 | Partial Approval | BRIAN MILLER |
| Sub-Drain | 2/25/2022 | Not Ready for Inspection | TIMOTHY POWELL |
| Approved Compaction Report | 5/17/2024 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Bottom/Toe | 7/10/2024 | Approved | MANUEL TEJADA |
| Final | 7/10/2024 | Not Ready for Inspection | MANUEL TEJADA |
| Rough | 7/10/2024 | Approved | MANUEL TEJADA |
| Approved Compaction Report | 7/12/2024 | Corrections Issued | MANUEL TEJADA |
| Approved Compaction Report | 7/15/2024 | Approved | MANUEL TEJADA |
| Final | 7/15/2024 | Permit Finaled | MANUEL TEJADA |