1400 N BENEDICT CANYON DR 90210

Certificate Information: 1400 N BENEDICT CANYON DR 90210

Application / Permit
19030-30000-07153
Plan Check / Job No.
B19WL06196
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
GRADING FOR 2-STORY ADDITION W/ 2-LEVELS OF BASEMENT
Permit Issued
Issued on 9/16/2020
Issuing Office
Current Status
Permit Finaled on 7/24/2024

Permit Application Status History

Submitted 11/5/2019 APPLICANT
Assigned to Plan Check Engineer 11/26/2019 REZA HAGHIGHAT
Corrections Issued 12/2/2019 REZA HAGHIGHAT
Quality Review Completed 12/13/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 2/4/2020 REZA HAGHIGHAT
Applicant returned to address corrections 5/11/2020 REZA HAGHIGHAT
Applicant returned to address corrections 5/14/2020 REZA HAGHIGHAT
Applicant returned to address corrections 5/15/2020 REZA HAGHIGHAT
Applicant returned to address corrections 5/20/2020 REZA HAGHIGHAT
Applicant returned to address corrections 6/3/2020 REZA HAGHIGHAT
Applicant returned to address corrections 7/27/2020 REZA HAGHIGHAT
Green Plans Picked Up 8/7/2020 APPLICANT
Plan Check Approved 8/26/2020 REZA HAGHIGHAT
Issued 9/16/2020 APPLICANT
Building Plans Picked Up 1/5/2021 APPLICANT
Permit Finaled 7/23/2024 ALEXANDER HELFER

Permit Application Clearance Information

Grading Pre-Inspection Cleared 7/25/2020 REZA HAGHIGHAT

Contact Information

Contractor Hansen Construction & Development; Lic. No.: 1057777-B 1806 CONEJO LANE      FULLERTON, CA 92833
Engineer De, Leon, Cynthia Aguilar; Lic. No.: C31604 8061 SAN MATEO CIR      BUENA PARK, CA 90620
Engineer Sun,, George Yu-Long; Lic. No.: S4576 16969 VON KARMAN 240      IRVINE, CA 92606
Geologist , ; Lic. No.: GEO2985    17106 CEREDO PL    GRANADA HILLS, CA 91344

Inspector Information

ROBERT PINA, (213) 482-0404 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 9/28/2020 Approved VASIL MIHALEV
Bottom/Toe 11/12/2020 Approved VASIL MIHALEV
Excavation 11/12/2020 Approved VASIL MIHALEV
Drainage Devices/Catch Basin 12/4/2020 Not Ready for Inspection VASIL MIHALEV
Sub-Drain 4/26/2021 Partial Approval ALEXANDER HELFER
Approved Compaction Report 5/23/2024 Approved ALEXANDER HELFER
Final 7/23/2024 Permit Finaled ALEXANDER HELFER
Rough 7/23/2024 Approved ALEXANDER HELFER