2714 W ANGUS ST 90039

Certificate Information: 2714 W ANGUS ST 90039

Application / Permit
19030-30000-06376
Plan Check / Job No.
B19WL05549
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
GRADING FOR (N) DETACHED GARAGE, (N) RETAINING & PLANTER WALLS
Permit Issued
Issued on 4/20/2021
Issuing Office
Current Status
Permit Finaled on 3/18/2025

Permit Application Status History

Submitted 10/2/2019 APPLICANT
Assigned to Plan Check Engineer 10/10/2019 VLADIMIR ARUTYUNYAN
Corrections Issued 10/17/2019 VLADIMIR ARUTYUNYAN
Green Plans Picked Up 10/29/2019 APPLICANT
Quality Review Completed 10/31/2019 FELIX FIGUEROA
Plan Check Approved 7/2/2020 VLADIMIR ARUTYUNYAN
Building Plans Picked Up 7/6/2020 APPLICANT
Issued 4/20/2021 APPLICANT
Permit Finaled 3/17/2025 RUSSELL BONVOULOIR

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,
Engineer Baad,, Katherine Firestone; Lic. No.: C64669 5232 ZAKON RD      TORRANCE, CA 90505

Inspector Information

RAMAZANALI ALMASI, (213) 482-0398 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 1/21/2022 Approved ROBERT HUGHES
Initial Grading 6/8/2022 Approved ROBERT HUGHES
Initial Grading 12/16/2022 Approved ROBERT HUGHES
Deputy Grading 1/23/2023 Conditional Approval LANNY MERRICK
Deputy Grading 1/24/2023 Conditional Approval LANNY MERRICK
Deputy Grading 1/25/2023 Approved ALEXANDER HELFER
Drainage Devices/Catch Basin 4/17/2023 Partial Approval LANNY MERRICK
Excavation 5/2/2023 Partial Approval LANNY MERRICK
Excavation 5/22/2023 Conditional Approval LANNY MERRICK
Bottom/Toe 5/23/2023 Not Ready for Inspection LANNY MERRICK
Sub-Drain 6/1/2023 Approved LANNY MERRICK
Drainage Devices/Catch Basin 9/10/2024 Corrections Issued RUSSELL BONVOULOIR
Bottom/Toe 2/24/2025 Approved RUSSELL BONVOULOIR
Final 2/24/2025 Corrections Issued RUSSELL BONVOULOIR
Rough 2/24/2025 Approved RUSSELL BONVOULOIR
Approved Compaction Report 3/7/2025 Approved LANNY MERRICK
Final 3/17/2025 Permit Finaled RUSSELL BONVOULOIR