1907 N NOLDEN ST 90041
Certificate Information: 1907 N NOLDEN ST 90041
- Application / Permit
- 19030-30000-04956
- Plan Check / Job No.
- B19WL03728
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- Grading for basement wall waterproofing. remove and recompact 35.17cy along south side of existing SFD.
- Permit Issued
- Issued on 3/10/2020
- Issuing Office
- West Los Angeles
- Current Status
- Permit Finaled on 5/6/2020
Permit Application Status History
| Submitted | 8/2/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/2/2019 | KAVIAN REFAHI |
| Corrections Issued | 10/28/2019 | KAVIAN REFAHI |
| Quality Review Completed | 10/28/2019 | TARIK SAOUD |
| Building Plans Picked Up | 10/28/2019 | APPLICANT |
| Applicant returned to address corrections | 2/25/2020 | KAVIAN REFAHI |
| Plan Check Approved | 3/10/2020 | KAVIAN REFAHI |
| Issued | 3/10/2020 | LADBS |
| Permit Finaled | 5/5/2020 | ROBERT HUGHES |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/27/2019 | KAVIAN REFAHI |
| Excavation more than 5-ft deep | Cleared | 3/10/2020 | CALOSHA APPROVED |
| Miscellaneous | Cleared | 3/10/2020 | KAVIAN REFAHI |
| ZA Case | Cleared | 3/10/2020 | SARAH GOLDMAN |
Contact Information
| Contractor | California Foundation Works Inc; Lic. No.: 976188-B | PO BOX 11099 LOS ANGELES, CA 90011 |
| Engineer | Cai,, Luo B; Lic. No.: C80352 | 9428 ETAON AVE M CHATSWORTH, CA 91311 |
| Engineer | Chiu,, Ivan Wai-Kuen; Lic. No.: C44672 | 2160 PARNELL WY ALTADENA, CA 91001 |
| Geologist | Tsao,, Tze-Tzong; Lic. No.: EG1783 | 9428 ETON AVENUE #M CHATSWORTH, CA 91311 |
Inspector Information
| JONATHAN HOM, (213) 482-7452 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT HUGHES, (213) 482-7452 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation | 3/23/2020 | Partial Approval | TODD MALAND |
| Bottom/Toe | 4/8/2020 | Partial Approval | ROBERT HUGHES |
| Sub-Drain | 4/8/2020 | Partial Approval | ROBERT HUGHES |
| Bottom/Toe | 4/21/2020 | Partial Approval | ROBERT HUGHES |
| Sub-Drain | 4/21/2020 | Partial Approval | ROBERT HUGHES |
| Bottom/Toe | 4/28/2020 | Approved | ROBERT HUGHES |
| Final | 4/28/2020 | Not Ready for Inspection | ROBERT HUGHES |
| Initial Grading | 4/28/2020 | Approved | ROBERT HUGHES |
| Rough | 4/28/2020 | Not Ready for Inspection | ROBERT HUGHES |
| Approved Compaction Report | 4/29/2020 | Approved | VASIL MIHALEV |
| Final | 5/5/2020 | Permit Finaled | ROBERT HUGHES |
| Rough | 5/5/2020 | Approved | ROBERT HUGHES |