878 N MORAGA DR 90049

Certificate Information: 878 N MORAGA DR 90049

Application / Permit
19030-30000-04720
Plan Check / Job No.
B19WL04188
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
GRADING FOR (N) POOL & RETAINING WALL
Permit Issued
Issued on 7/10/2020
Issuing Office
Current Status
Permit Finaled on 9/9/2022

Permit Application Status History

Submitted 7/24/2019 APPLICANT
Assigned to Plan Check Engineer 8/8/2019 TSE MING HUANG
Corrections Issued 8/23/2019 STANLEY RAAP
Quality Review Completed 8/24/2019 STANLEY RAAP
Plan Check Approved 2/5/2020 TSE MING HUANG
Issued 7/10/2020 APPLICANT
Building Plans Picked Up 5/21/2021 APPLICANT
Permit Finaled 9/9/2022 TIMOTHY POWELL

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/10/2019 DINAH GARIN
Drainage to Storm Drain Cleared 1/2/2020 DINAH GARIN

Contact Information

Contractor Kinner Ray Builders; Lic. No.: 240260-B 212 26TH STREET      SANTA MONICA, CA 90402
Engineer Berkoz,, Ertunga; Lic. No.: S2504 4665 ELLENITA AVE      TARZANA, CA 91356

Inspector Information

GERMAN RODRIGUEZ MENDOZA, (310) 914-3932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 7/23/2020 Approved BRIAN OLSON
Excavation 9/10/2020 Partial Inspection BRIAN OLSON
Sub-Drain 11/17/2020 Partial Inspection BRIAN OLSON
Drainage Devices/Catch Basin 11/30/2020 Partial Approval KIRK LINKLATER
Deputy Grading 12/1/2020 Approved BRIAN OLSON
Sub-Drain 5/3/2021 Partial Approval BRIAN OLSON
Drainage Devices/Catch Basin 10/1/2021 Approved VASIL MIHALEV
Special/Order Compliance 10/1/2021 Not Ready for Inspection VASIL MIHALEV
Bottom/Toe 11/15/2021 Partial Approval CHARLES POWELL
Drainage Devices/Catch Basin 11/15/2021 Partial Approval CHARLES POWELL
FLOOD-Elevation Certificate 11/15/2021 Not Ready for Inspection CHARLES POWELL
Bottom/Toe 4/25/2022 Not Ready for Inspection JONATHAN HOM
Final 4/25/2022 Not Ready for Inspection JONATHAN HOM
Rough 4/25/2022 Not Ready for Inspection JONATHAN HOM
Special/Order Compliance 4/26/2022 Not Ready for Inspection TIMOTHY POWELL
Special/Order Compliance 5/4/2022 Corrections Issued CHARLES POWELL
Approved Compaction Report 5/12/2022 Partial Approval CHARLES POWELL
Final 5/18/2022 Not Ready for Inspection CHARLES POWELL
Bottom/Toe 9/2/2022 Approved TIMOTHY POWELL
Final 9/2/2022 Not Ready for Inspection TIMOTHY POWELL
Rough 9/2/2022 Approved TIMOTHY POWELL
Final 9/9/2022 Permit Finaled TIMOTHY POWELL