10768 W BELLAGIO ROAD 90077
Certificate Information: 10768 W BELLAGIO ROAD 90077
- Application / Permit
- 19030-30000-04200
- Plan Check / Job No.
- B19WL03698
- Group
- Building
- Type
- Grading
- Sub-Type
- Commercial
- Primary Use
- (70) Grading - Hillside
- Work Description
- site grading for new clubhouse, retaining wallls, and guesthouse.
- Permit Issued
- Issued on 8/19/2020
- Issuing Office
- Current Status
- Permit Finaled on 2/12/2026
Permit Application Status History
| Submitted | 7/2/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/24/2019 | TARIK SAOUD |
| Corrections Issued | 7/29/2019 | TARIK SAOUD |
| Quality Review Completed | 8/15/2019 | FELIX FIGUEROA |
| Disabled Access Plans Picked Up | 8/20/2019 | APPLICANT |
| Green Plans Picked Up | 6/9/2020 | APPLICANT |
| Applicant returned to address corrections | 8/3/2020 | TARIK SAOUD |
| Plan Check Approved | 8/4/2020 | TARIK SAOUD |
| Issued | 8/19/2020 | APPLICANT |
| Building Plans Picked Up | 9/2/2020 | APPLICANT |
| Permit Finaled | 2/11/2026 | GERMAN RODRIGUEZ MENDOZA |
Permit Application Clearance Information
| CPC | Cleared | 10/3/2019 | JOE LUCKEY |
| ZA Case | Cleared | 10/3/2019 | JOE LUCKEY |
| ZA Case | Cleared | 2/11/2020 | RICHARD REASER |
| Trees in Parkway | Cleared | 2/15/2020 | ADRIAN SANCHEZ |
| ZA Case | Cleared | 2/20/2020 | DENZEL HENDERSON |
| Eng Process Fee Ord 176,300 | Cleared | 2/26/2020 | OSCAR GUTIERREZ |
| Grading in hillside | Cleared | 2/28/2020 | NOAH MCCOY |
| Miscellaneous | Cleared | 2/28/2020 | NOAH MCCOY |
| Site Plan review | Cleared | 2/28/2020 | NOAH MCCOY |
| Miscellaneous | Cleared | 3/3/2020 | NOAH MCCOY |
| Construction near power lines | Cleared | 4/13/2020 | WALTER RAMIREZ |
| Work Adjacent to Public Way | Cleared | 6/23/2020 | SAUL GARCIA |
| Low Impact Development | Cleared | 7/8/2020 | AMMAR ELTAWIL |
| Excavation more than 5-ft deep | Cleared | 7/14/2020 | CALOSHA APPROVED |
Contact Information
| Architect | Marsh,, Michael Steven; Lic. No.: C23523 | 15900 LA CANTERA PARKWAY SUITE 19205 SAN ANTONIO, TX 78256 |
| Contractor | Hayhoe Construction Corporation; Lic. No.: 519186-B | 17821 EAST 17TH STREET STE 150 TUSTIN, CA 92780 |
| Engineer | Leffler,, Russell David; Lic. No.: C65053 | 165 S UNION BLVD STE 360 LAKEWOOD, CO 80228 |
| Engineer | Liston,, Leonard Irvin; Lic. No.: C31902 | 889 PIERCE CT STE 101 THOUSAND OAKS, CA 91360 |
| Geologist | Holt,, Jacob William; Lic. No.: EG2282 | 5158 COCHRAN ST SIMI VALLEY, CA 93063 |
Inspector Information
| GERMAN RODRIGUEZ MENDOZA, (310) 914-3932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 1/15/2021 | Partial Approval | BRIAN OLSON |
| Bottom/Toe | 4/21/2021 | Partial Approval | BRIAN OLSON |
| Deputy Grading | 4/21/2021 | Approved | BRIAN OLSON |
| Excavation | 4/21/2021 | Partial Approval | BRIAN OLSON |
| Initial Grading | 4/21/2021 | Approved | BRIAN OLSON |
| Deputy Grading | 4/22/2021 | Conditional Approval | BRIAN OLSON |
| Deputy Grading | 4/23/2021 | Conditional Approval | BRIAN OLSON |
| Deputy Grading | 4/26/2021 | Approved | BRIAN OLSON |
| Deputy Grading | 4/27/2021 | Conditional Approval | BRIAN OLSON |
| Bottom/Toe | 4/28/2021 | Partial Approval | BRIAN OLSON |
| Deputy Grading | 4/28/2021 | Approved | BRIAN OLSON |
| Deputy Grading | 4/29/2021 | Conditional Approval | BRIAN OLSON |
| Bottom/Toe | 4/30/2021 | Partial Approval | BRIAN OLSON |
| Deputy Grading | 4/30/2021 | Approved | BRIAN OLSON |
| Bottom/Toe | 5/3/2021 | Partial Approval | BRIAN OLSON |
| Deputy Grading | 5/3/2021 | Approved | BRIAN OLSON |
| Deputy Grading | 5/4/2021 | Conditional Approval | BRIAN OLSON |
| Bottom/Toe | 5/5/2021 | Partial Inspection | BRIAN OLSON |
| Deputy Grading | 5/5/2021 | Approved | BRIAN OLSON |
| Bottom/Toe | 5/6/2021 | Partial Approval | BRIAN OLSON |
| Deputy Grading | 5/6/2021 | Approved | BRIAN OLSON |
| Deputy Grading | 5/7/2021 | Approved | BRIAN OLSON |
| Deputy Grading | 5/10/2021 | Approved | BRIAN OLSON |
| Deputy Grading | 5/11/2021 | Approved | BRIAN OLSON |
| Deputy Grading | 5/12/2021 | Approved | BRIAN OLSON |
| Deputy Grading | 5/13/2021 | Approved | JONATHAN HOM |
| Bottom/Toe | 5/14/2021 | Partial Approval | BRIAN OLSON |
| Deputy Grading | 5/14/2021 | Approved | BRIAN OLSON |
| Drainage Devices/Catch Basin | 7/7/2021 | Partial Inspection | BRIAN OLSON |
| Excavation | 7/7/2021 | Partial Inspection | BRIAN OLSON |
| Sub-Drain | 7/7/2021 | Partial Inspection | BRIAN OLSON |
| Drainage Devices/Catch Basin | 7/13/2021 | Partial Approval | BRIAN OLSON |
| Drainage Devices/Catch Basin | 7/15/2021 | Partial Approval | JONATHAN HOM |
| Sub-Drain | 7/15/2021 | Partial Inspection | JONATHAN HOM |
| Initial Grading | 1/13/2022 | Partial Inspection | JONATHAN HOM |
| Rough | 1/13/2022 | Partial Inspection | JONATHAN HOM |
| Bottom/Toe | 1/21/2022 | Partial Approval | CHARLES POWELL |
| Bottom/Toe | 4/11/2022 | Partial Approval | CHARLES POWELL |
| Bottom/Toe | 6/9/2022 | Partial Approval | CHARLES POWELL |
| Rough | 6/9/2022 | Partial Approval | CHARLES POWELL |
| Sub-Drain | 12/8/2022 | Partial Approval | CHARLES POWELL |
| Sub-Drain | 7/14/2023 | Not Ready for Inspection | CHARLES POWELL |
| Approved Compaction Report | 12/19/2023 | Approved | CHARLES POWELL |
| Sub-Drain | 5/1/2024 | Not Ready for Inspection | VASIL MIHALEV |
| Initial Grading | 5/23/2024 | Partial Approval | JOHNNY MIRANDA |
| Final | 8/28/2024 | Not Ready for Inspection | AL GAMBLE |
| Final | 9/3/2024 | Corrections Issued | JOHNNY MIRANDA |
| Bottom/Toe | 9/4/2024 | Not Ready for Inspection | MATTHEW JENKINS |
| Drainage Devices/Catch Basin | 9/4/2024 | Not Ready for Inspection | MATTHEW JENKINS |
| Final | 9/4/2024 | Not Ready for Inspection | MATTHEW JENKINS |
| Rough | 9/4/2024 | Not Ready for Inspection | MATTHEW JENKINS |
| Final | 9/11/2024 | Not Ready for Inspection | AL GAMBLE |
| Approved Compaction Report | 9/12/2024 | Partial Inspection | MATTHEW JENKINS |
| Approved Compaction Report | 9/24/2024 | Corrections Issued | VASIL MIHALEV |
| Approved Compaction Report | 10/28/2024 | Approved | VASIL MIHALEV |
| Deputy Grading | 1/10/2025 | Conditional Approval | JOHNNY MIRANDA |
| Initial Grading | 1/13/2025 | Approved | VASIL MIHALEV |
| Deputy Grading | 1/14/2025 | No Access for Inspection | VASIL MIHALEV |
| Bottom/Toe | 1/15/2025 | Partial Inspection | MATTHEW JENKINS |
| Deputy Grading | 1/16/2025 | Conditional Approval | MATTHEW JENKINS |
| Bottom/Toe | 1/17/2025 | Partial Inspection | MATTHEW JENKINS |
| Deputy Grading | 1/17/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 1/21/2025 | Conditional Approval | JOHNNY MIRANDA |
| Deputy Grading | 1/23/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 1/27/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 1/28/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 1/31/2025 | Conditional Approval | MATTHEW JENKINS |
| Rough | 1/31/2025 | Corrections Issued | MATTHEW JENKINS |
| Deputy Grading | 2/3/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 2/4/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 2/10/2025 | No Access for Inspection | MATTHEW JENKINS |
| Deputy Grading | 2/11/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 2/12/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 2/18/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 2/19/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 2/20/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 2/24/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 2/25/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 2/27/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 2/28/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 3/3/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 3/4/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 3/5/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 3/6/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 3/7/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 3/11/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 3/17/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 3/18/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 3/19/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 3/20/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 3/21/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 3/24/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 3/25/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 3/26/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 3/27/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 3/28/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 4/1/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 4/2/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 4/3/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 4/4/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 4/7/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 4/8/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 4/9/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 4/10/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 4/11/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 4/15/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 4/23/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 4/24/2025 | Conditional Approval | JOHNNY MIRANDA |
| Deputy Grading | 4/25/2025 | Conditional Approval | JOHNNY MIRANDA |
| Deputy Grading | 5/2/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 5/7/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 5/8/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 5/9/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 5/12/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 5/14/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 5/16/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 5/19/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 5/20/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 5/22/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 5/28/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 5/29/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 6/2/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 6/3/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 6/4/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 6/5/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 6/9/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 6/10/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 6/11/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 6/12/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 6/13/2025 | Conditional Approval | JOHNNY MIRANDA |
| Deputy Grading | 6/16/2025 | Conditional Approval | AL GAMBLE |
| Deputy Grading | 6/17/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 6/18/2025 | Conditional Approval | MATTHEW JENKINS |
| Sub-Drain | 6/18/2025 | Partial Approval | MATTHEW JENKINS |
| Deputy Grading | 6/20/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 6/25/2025 | Approved | ROBERT PINA |
| Deputy Grading | 6/26/2025 | Conditional Approval | JOHNNY MIRANDA |
| Deputy Grading | 7/1/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 7/2/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 7/7/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 7/8/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 7/10/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 7/11/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 7/14/2025 | Conditional Approval | MATTHEW JENKINS |
| Drainage Devices/Catch Basin | 7/14/2025 | Partial Approval | MATTHEW JENKINS |
| Deputy Grading | 8/6/2025 | Conditional Approval | LANNY MERRICK |
| Bottom/Toe | 9/2/2025 | Partial Inspection | MATTHEW JENKINS |
| Deputy Grading | 9/9/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 9/10/2025 | Conditional Approval | JOHNNY MIRANDA |
| Deputy Grading | 9/11/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 9/12/2025 | Conditional Approval | MATTHEW JENKINS |
| Sub-Drain | 9/12/2025 | Partial Approval | MATTHEW JENKINS |
| Deputy Grading | 10/6/2025 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Grading | 10/7/2025 | Approved | ROBERT PINA |
| Deputy Grading | 10/20/2025 | Conditional Approval | LANNY MERRICK |
| Deputy Grading | 10/30/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 11/3/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 11/4/2025 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 11/25/2025 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Deputy Grading | 12/10/2025 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Deputy Grading | 12/16/2025 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Deputy Grading | 1/13/2026 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Bottom/Toe | 1/26/2026 | Approved | JOHNNY MIRANDA |
| Final | 1/26/2026 | Not Ready for Inspection | JOHNNY MIRANDA |
| Rough | 1/26/2026 | Approved | JOHNNY MIRANDA |
| Final | 2/3/2026 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Final | 2/11/2026 | Permit Finaled | GERMAN RODRIGUEZ MENDOZA |