10542 W WILKINS AVE 90024
Certificate Information: 10542 W WILKINS AVE 90024
- Application / Permit
- 19030-30000-04195
- Plan Check / Job No.
- B19WL03689
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- Grading for a new retaining wall
- Permit Issued
- Issued on 9/4/2020
- Issuing Office
- Current Status
- Permit Finaled on 4/13/2021
Permit Application Status History
| Submitted | 7/1/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/1/2019 | KAVIAN REFAHI |
| Corrections Issued | 8/7/2019 | KAVIAN REFAHI |
| Quality Review Completed | 8/16/2019 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 8/13/2020 | KAVIAN REFAHI |
| Plan Check Approved | 8/20/2020 | KAVIAN REFAHI |
| Issued | 9/4/2020 | APPLICANT |
| Building Plans Picked Up | 9/17/2020 | APPLICANT |
| Permit Finaled | 4/12/2021 | BRIAN OLSON |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 8/20/2020 | KAVIAN REFAHI |
Contact Information
| Contractor | Smith Robert; Lic. No.: 888378-B | 1321 BERYL ST #204 REDONDO BEACH, CA 90277 |
| Engineer | Irvine,, Jon Alan; Lic. No.: GE2891 | 145 N SIERRA MADRE BLVD STE 1 PASADENA, CA 91107 |
| Engineer | Mallak,, Nabil Michel; Lic. No.: S5351 | 3679 MOTOR AVE SUITE 201 LOS ANGELES, CA 90034 |
Inspector Information
| JOHNNY MIRANDA, (310) 914-3937 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 10/8/2020 | Partial Inspection | KIRK LINKLATER |
| Sub-Drain | 10/22/2020 | Partial Inspection | JONATHAN HOM |
| Sub-Drain | 10/23/2020 | Partial Approval | MATTHEW JENKINS |
| Bottom/Toe | 11/16/2020 | Partial Approval | MATTHEW JENKINS |
| Sub-Drain | 11/20/2020 | Partial Approval | MATTHEW JENKINS |
| Bottom/Toe | 12/11/2020 | Not Ready for Inspection | JONATHAN HOM |
| Final | 12/11/2020 | Partial Inspection | JONATHAN HOM |
| Rough | 12/11/2020 | Not Ready for Inspection | JONATHAN HOM |
| Bottom/Toe | 12/21/2020 | Approved | KIRK LINKLATER |
| Final | 12/21/2020 | Corrections Issued | KIRK LINKLATER |
| Rough | 12/21/2020 | Approved | KIRK LINKLATER |
| Approved Compaction Report | 3/1/2021 | Approved | KIRK LINKLATER |
| Final | 4/12/2021 | Permit Finaled | BRIAN OLSON |