8848 W APPIAN WAY 90046

Certificate Information: 8848 W APPIAN WAY 90046

Application / Permit
19030-30000-03793
Plan Check / Job No.
B19WL03331
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
Grading for new SFD
Permit Issued
Issued on 1/16/2025
Issuing Office
West Los Angeles
Current Status
Issued on 1/16/2025

Permit Application Status History

Submitted 6/13/2019 APPLICANT
Assigned to Plan Check Engineer 7/11/2019 TARIK SAOUD
Corrections Issued 7/15/2019 TARIK SAOUD
Quality Review Completed 7/17/2019 FELIX FIGUEROA
Applicant returned to address corrections 6/28/2021 TARIK SAOUD
Applicant returned to address corrections 4/1/2022 TARIK SAOUD
Applicant returned to address corrections 7/8/2022 TARIK SAOUD
Building Plans Picked Up 7/14/2022 APPLICANT
Applicant returned to address corrections 3/16/2023 YASHAR EMAMI
Applicant returned to address corrections 4/11/2023 YASHAR EMAMI
Applicant returned to address corrections 4/18/2023 YASHAR EMAMI
Green Plans Picked Up 4/24/2023 APPLICANT
Applicant returned to address corrections 9/29/2023 YASHAR EMAMI
Applicant returned to address corrections 10/4/2023 YASHAR EMAMI
Plan Check Approved 7/11/2024 YASHAR EMAMI
Issued 1/16/2025 APPLICANT

Permit Application Clearance Information

CPC Cleared 7/19/2019 NOAH MCCOY
Construction near power lines Cleared 8/29/2019 RIDWAN HARDY
Low Impact Development Cleared 2/24/2023 CHRIS VONG
Excavation more than 5-ft deep Cleared 6/11/2024 CALOSHA APPROVED
Grading Pre-Inspection Cleared 6/11/2024 TARIK SAOUD

Contact Information

Contractor Owner-Builder       ,
Engineer Larocca,, Francis; Lic. No.: C75121 2008A BELMONT LANE      REDONDO BEACH, CA 90278

Inspector Information

ROBERT PINA, (213) 482-0404 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 8/26/2025 Approved ROBERT PINA
Special/Order Compliance 9/25/2025 Approved ROBERT PINA
Deputy Grading 9/29/2025 Approved ROBERT PINA
Deputy Grading 9/30/2025 Approved ROBERT PINA
Deputy Grading 10/21/2025 Approved ROBERT PINA
Deputy Grading 10/22/2025 Approved ROBERT PINA
Deputy Grading 12/11/2025 Approved ROBERT PINA
Deputy Grading 12/12/2025 Approved ROBERT PINA
Excavation 2/9/2026 Partial Inspection RAMAZANALI ALMASI
Deputy Grading 3/13/2026 Approved ROBERT PINA
Excavation 4/1/2026 Approved ROBERT PINA
Sub-Drain 5/1/2026 Conditional Approval ROBERT PINA
Excavation 5/12/2026 Conditional Approval ROBERT PINA
Bottom/Toe 6/1/2026 Approved ROBERT PINA
Final 6/1/2026 Not Ready for Inspection ROBERT PINA
Rough 6/1/2026 Approved ROBERT PINA