2119 W EWING ST 90039

Certificate Information: 2119 W EWING ST 90039

Application / Permit
19030-30000-02948
Plan Check / Job No.
B19WL02612
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
Grading for new single family dwelling
Permit Issued
Issued on 6/15/2023
Issuing Office
Metro
Current Status
Permit Finaled on 5/7/2026

Permit Application Status History

Submitted 5/10/2019 APPLICANT
Assigned to Plan Check Engineer 6/13/2019 MARJAN SHENASI
Corrections Issued 6/18/2019 MARJAN SHENASI
Quality Review Completed 6/25/2019 KAMRAN GHOTBI RAVANDI
Green Plans Picked Up 6/25/2019 APPLICANT
Applicant returned to address corrections 7/13/2021 MARJAN SHENASI
Applicant returned to address corrections 7/19/2021 MARJAN SHENASI
Applicant returned to address corrections 12/20/2021 MARJAN SHENASI
Applicant returned to address corrections 12/27/2021 MARJAN SHENASI
Applicant returned to address corrections 9/16/2022 YASHAR EMAMI
Plan Check Approved 10/6/2022 YASHAR EMAMI
Building Plans Picked Up 10/6/2022 APPLICANT
Issued 6/15/2023 APPLICANT
Permit Finaled 5/1/2026 JONATHAN HOM

Permit Application Clearance Information

Encroachment in public way Cleared 7/15/2019 KARAN PATEL
Eng Process Fee Ord 176,300 Cleared 7/15/2019 KARAN PATEL
Work Adjacent to Public Way Cleared 4/21/2022 ARMEN SARKISIAN
Excavation more than 5-ft deep Cleared 6/15/2023 CALOSHA APPROVED
GPI Written Notices Cleared 6/15/2023 MARJAN SHENASI
Grading Pre-Inspection Cleared 6/15/2023 MARJAN SHENASI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JONATHAN HOM, (213) 482-7452 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT HUGHES, (213) 482-7452 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 7/11/2023 Partial Approval ROBERT HUGHES
Sub-Drain 9/25/2023 Partial Approval ROBERT HUGHES
Sub-Drain 2/27/2024 Partial Approval RUSSELL BONVOULOIR
Approved Compaction Report 11/17/2025 Approved RAMAZANALI ALMASI
Bottom/Toe 1/29/2026 Partial Inspection JONATHAN HOM
Final 1/29/2026 Corrections Issued JONATHAN HOM
Rough 1/29/2026 Partial Inspection JONATHAN HOM
Bottom/Toe 2/5/2026 Not Ready for Inspection JONATHAN HOM
Final 2/5/2026 Corrections Issued JONATHAN HOM
Rough 2/5/2026 Not Ready for Inspection JONATHAN HOM
Bottom/Toe 5/1/2026 Approved JONATHAN HOM
Final 5/1/2026 Permit Finaled JONATHAN HOM
Rough 5/1/2026 Approved JONATHAN HOM