1963 N STRADELLA ROAD 90077

Certificate Information: 1963 N STRADELLA ROAD 90077

Application / Permit
19030-30000-01943
Plan Check / Job No.
B19WL01680
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
Site Grading for new single family dwelling with basement, new site retaining walls, detached deck, new pool.
Permit Issued
Issued on 7/23/2020
Issuing Office
Current Status
Permit Finaled on 6/30/2025

Permit Application Status History

Submitted 3/28/2019 APPLICANT
Assigned to Plan Check Engineer 4/11/2019 KAMRAN GHOTBI RAVANDI
Corrections Issued 4/15/2019 KAMRAN GHOTBI RAVANDI
Quality Review Completed 4/17/2019 CORA JOHNSON
Green Plans Picked Up 4/30/2019 APPLICANT
Applicant returned to address corrections 5/30/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 6/20/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 8/19/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 10/4/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 5/7/2020 KAMRAN GHOTBI RAVANDI
Plan Check Approved 5/28/2020 KAMRAN GHOTBI RAVANDI
Issued 7/23/2020 APPLICANT
Building Plans Picked Up 8/7/2020 APPLICANT
Permit Finaled 6/30/2025 MATTHEW JENKINS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/19/2019 JENNY CEA
Excavation more than 5-ft deep Cleared 8/19/2019 CALOSHA APPROVED
Work Adjacent to Public Way Cleared 8/19/2019 JENNY CEA
ZI Cleared 8/19/2019 SARAH GOLDMAN
Haul Route Cleared 5/28/2020 KAMRAN GHOTBI RAVANDI

Contact Information

Contractor Owner-Builder       ,
Engineer Eftekhari,, Hossein; Lic. No.: C50121 5945 SETTLER COURT      ANAHEIM, CA 92807
Engineer Kamboj,, Naresh Chander; Lic. No.: C21893 7838 QUIMBY AVE      CANOGA PARK, CA 91304
Geologist Bramwell,, David Delton; Lic. No.: EG112 GLOBAL GEOLOGICAL SERVICES   983 RIDGEWOOD DR    CORONA, CA 91719

Inspector Information

GERMAN RODRIGUEZ MENDOZA, (310) 914-3932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 9/3/2020 Corrections Issued BRIAN OLSON
Excavation 9/9/2020 Partial Inspection BRIAN OLSON
Initial Grading 9/9/2020 Approved BRIAN OLSON
Special/Order Compliance 10/19/2020 Corrections Issued BRIAN OLSON
Special/Order Compliance 12/10/2020 Partial Inspection BRIAN OLSON
Sub-Drain 2/3/2021 Partial Approval BRIAN OLSON
Sub-Drain 3/17/2021 Partial Approval BRIAN OLSON
Sub-Drain 3/31/2021 Partial Approval BRIAN OLSON
Sub-Drain 4/20/2021 Partial Approval BRIAN OLSON
Sub-Drain 10/13/2021 Partial Approval JONATHAN HOM
Special/Order Compliance 11/2/2021 Corrections Issued CHARLES POWELL
Special/Order Compliance 11/10/2021 Partial Approval CHARLES POWELL
Sub-Drain 2/16/2022 Partial Approval CHARLES POWELL
Sub-Drain 6/29/2022 Partial Approval TIMOTHY POWELL
Fill/Backfill 12/17/2024 Partial Inspection JOHNNY MIRANDA
Bottom/Toe 1/14/2025 Corrections Issued VASIL MIHALEV
Final 1/14/2025 Not Ready for Inspection VASIL MIHALEV
Rough 1/14/2025 Approved VASIL MIHALEV
Approved Compaction Report 2/4/2025 Approved MATTHEW JENKINS
Bottom/Toe 4/24/2025 Not Ready for Inspection JOHNNY MIRANDA
Final 4/24/2025 Corrections Issued JOHNNY MIRANDA
Bottom/Toe 4/29/2025 Partial Inspection MATTHEW JENKINS
Final 4/29/2025 Corrections Issued MATTHEW JENKINS
Approved Compaction Report 5/14/2025 Approved MATTHEW JENKINS
Bottom/Toe 6/18/2025 Partial Inspection MATTHEW JENKINS
Final 6/18/2025 Partial Inspection MATTHEW JENKINS
Bottom/Toe 6/30/2025 Approved MATTHEW JENKINS
Final 6/30/2025 Permit Finaled MATTHEW JENKINS