4427 E SAN ANDREAS AVE 90065
Certificate Information: 4427 E SAN ANDREAS AVE 90065
- Application / Permit
- 19030-20001-06194
- Plan Check / Job No.
- B22VN04247
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- GRADING FOR PROP. SFD AND RET WALL
- Permit Issued
- Issued on 12/20/2022
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 4/2/2025
Permit Application Status History
| Submitted | 3/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/14/2022 | SEAN SHAHMIRI |
| Corrections Issued | 4/25/2022 | SEAN SHAHMIRI |
| Quality Review Completed | 4/29/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 5/3/2022 | APPLICANT |
| Applicant returned to address corrections | 7/21/2022 | SEAN SHAHMIRI |
| Plan Check Approved | 7/27/2022 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 7/29/2022 | SEAN SHAHMIRI |
| Issued | 12/20/2022 | APPLICANT |
| Permit Finaled | 4/1/2025 | RUSSELL BONVOULOIR |
Permit Application Clearance Information
| Specific Plan | Cleared | 7/1/2022 | KENTON TRINH |
Contact Information
| Contractor | Hernz Construction Incorporated; Lic. No.: 581129-B | 8931 WOODMAN AVENUE PACOIMA, CA 91331 |
| Engineer | Chiu,, Ivan Wai-Kuen; Lic. No.: C44672 | 2160 PARNELL WY ALTADENA, CA 91001 |
Inspector Information
| JONATHAN HOM, (213) 482-7452 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT HUGHES, (213) 482-7452 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation | 3/7/2023 | Partial Approval | LANNY MERRICK |
| Excavation | 3/8/2023 | Not Ready for Inspection | LANNY MERRICK |
| Initial Grading | 4/11/2023 | Approved | ROBERT HUGHES |
| Sub-Drain | 8/16/2023 | Partial Approval | RUSSELL BONVOULOIR |
| Sub-Drain | 11/13/2023 | Partial Approval | ROBERT HUGHES |
| Sub-Drain | 2/26/2024 | Conditional Approval | JONATHAN HOM |
| Sub-Drain | 4/10/2024 | Approved | LANNY MERRICK |
| Bottom/Toe | 3/24/2025 | Not Ready for Inspection | RUSSELL BONVOULOIR |
| Final | 3/24/2025 | Corrections Issued | RUSSELL BONVOULOIR |
| Rough | 3/24/2025 | Not Ready for Inspection | RUSSELL BONVOULOIR |
| Bottom/Toe | 4/1/2025 | Approved | RUSSELL BONVOULOIR |
| Final | 4/1/2025 | Permit Finaled | RUSSELL BONVOULOIR |
| Rough | 4/1/2025 | Approved | RUSSELL BONVOULOIR |