17570 W DEARBORN ST 91325

Certificate Information: 17570 W DEARBORN ST 91325

Application / Permit
19030-20001-01963
Plan Check / Job No.
B19VN07268
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(60) Grading - Non-Hillside
Work Description
Supplemental Permit to 19030-20000-01963 to include Site Prep. into scope of work.
Permit Issued
Issued on 2/12/2020
Issuing Office
Valley
Current Status
Issued on 2/12/2020

Permit Application Status History

Submitted 5/3/2019 APPLICANT
Assigned to Plan Check Engineer 5/23/2019 OMID HEDAYAT
Corrections Issued 6/3/2019 OMID HEDAYAT
Quality Review Completed 6/3/2019 STEVEN KIM
Building Plans Picked Up 6/5/2019 APPLICANT
Applicant returned to address corrections 1/23/2020 OMID HEDAYAT
Plan Check Approved 1/23/2020 OMID HEDAYAT
Issued 2/12/2020 LADBS
Permit Finaled-Status Void 2/24/2021 ALEXANDER ANDREWS
Re-Activate Permit 6/23/2023 ALEXANDER ANDREWS

Permit Application Clearance Information

Miscellaneous Cleared 1/23/2020 STEVEN WECHSLER
ZA Case Cleared 1/23/2020 STEVEN WECHSLER

Contact Information

Contractor Amado Marble & Construction Inc; Lic. No.: 793379-B 15526 LANARK STREET      VAN NUYS, CA 91406
Engineer Majidi-Kh,, Yaghob; Lic. No.: C78005 427 N FLORENCE      BURBANK, CA 91505

Inspector Information

ALEXANDER HELFER, (818) 374-4354 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Bottom/Toe 8/12/2020 Partial Approval ALEXANDER ANDREWS
Approved Compaction Report 9/30/2020 Approved MANUEL TEJADA
Bottom/Toe 10/2/2020 Not Ready for Inspection KIRK LINKLATER
Final 10/2/2020 Not Ready for Inspection KIRK LINKLATER
Rough 10/2/2020 Not Ready for Inspection KIRK LINKLATER
Bottom/Toe 1/14/2021 Partial Approval ALEXANDER ANDREWS
Bottom/Toe 2/24/2021 Approved ALEXANDER ANDREWS
Final 2/24/2021 Conditional Approval ALEXANDER ANDREWS
Rough 2/24/2021 Approved ALEXANDER ANDREWS
Special/Order Compliance 6/27/2023 Corrections Issued BRIAN MILLER
Approved Compaction Report 6/29/2023 Not Ready for Inspection BRIAN MILLER
Drainage Devices/Catch Basin 6/29/2023 Partial Approval BRIAN MILLER
Excavation 6/29/2023 Partial Approval BRIAN MILLER
Approved Compaction Report 3/26/2024 Approved GERMAN RODRIGUEZ MENDOZA