926 N ILIFF ST 90272
Certificate Information: 926 N ILIFF ST 90272
- Application / Permit
- 19030-20000-08367
- Plan Check / Job No.
- B19VN22193
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- GRADING EXCAVATION FOR 2-STORY SFD WITH BASEMENT( 918 CY).
- Permit Issued
- Issued on 3/4/2020
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 3/10/2022
Permit Application Status History
| Submitted | 12/20/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/2/2020 | TROY DEGUZMAN |
| Corrections Issued | 1/4/2020 | TROY DEGUZMAN |
| Quality Review Completed | 1/21/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 1/24/2020 | APPLICANT |
| Green Plans Picked Up | 1/24/2020 | APPLICANT |
| Plan Check Approved | 2/26/2020 | TROY DEGUZMAN |
| Issued | 3/4/2020 | LADBS |
| Permit Finaled | 3/9/2022 | KIRK LINKLATER |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 3/4/2020 | TROY DEGUZMAN |
| Grading Pre-Inspection | Cleared | 3/4/2020 | TROY DEGUZMAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| RUSSELL BONVOULOIR, (310) 914-3899 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation | 10/13/2020 | Partial Inspection | MATTHEW JENKINS |
| Sub-Drain | 12/11/2020 | Partial Approval | MATTHEW JENKINS |
| Approved Compaction Report | 10/26/2021 | Approved | MATTHEW JENKINS |
| Bottom/Toe | 2/17/2022 | Not Ready for Inspection | MATTHEW JENKINS |
| Final | 2/17/2022 | Corrections Issued | MATTHEW JENKINS |
| Rough | 2/17/2022 | Not Ready for Inspection | MATTHEW JENKINS |
| Bottom/Toe | 2/23/2022 | Not Ready for Inspection | MATTHEW JENKINS |
| Final | 2/23/2022 | Not Ready for Inspection | MATTHEW JENKINS |
| Rough | 2/23/2022 | Not Ready for Inspection | MATTHEW JENKINS |
| Bottom/Toe | 3/1/2022 | Not Ready for Inspection | MATTHEW JENKINS |
| Final | 3/1/2022 | Not Ready for Inspection | MATTHEW JENKINS |
| Rough | 3/1/2022 | Not Ready for Inspection | MATTHEW JENKINS |
| Bottom/Toe | 3/4/2022 | Corrections Issued | CHARLES POWELL |
| Final | 3/4/2022 | Not Ready for Inspection | CHARLES POWELL |
| Rough | 3/4/2022 | Approved | CHARLES POWELL |
| Bottom/Toe | 3/9/2022 | Approved | KIRK LINKLATER |
| Final | 3/9/2022 | Permit Finaled | KIRK LINKLATER |