10218 N FERNGLEN AVE 91042

Certificate Information: 10218 N FERNGLEN AVE 91042

Application / Permit
19030-20000-08237
Plan Check / Job No.
B19VN21939
Group
Building
Type
Grading
Sub-Type
Apartment
Primary Use
(70) Grading - Hillside
Work Description
(3 OF 3) GRADING FOR (N) 3-STORY APT W/ BASEMENT
Permit Issued
Issued on 9/28/2021
Issuing Office
Valley
Current Status
Permit Finaled on 5/22/2025

Permit Application Status History

Submitted 12/18/2019 APPLICANT
Application Withdrawn 12/18/2019 APPLICANT
Re-Activate Applicaton 12/18/2019 APPLICANT
Assigned to Plan Check Engineer 1/16/2020 MARVEL DELACRUZ
Green Plans Picked Up 1/24/2020 APPLICANT
Corrections Issued 1/28/2020 MARVEL DELACRUZ
Disabled Access Plans Picked Up 1/28/2020 APPLICANT
Quality Review Completed 1/29/2020 STEVEN KIM
Building Plans Picked Up 1/30/2020 APPLICANT
Applicant returned to address corrections 5/1/2020 MARVEL DELACRUZ
Applicant returned to address corrections 12/1/2020 MARVEL DELACRUZ
Applicant returned to address corrections 12/3/2020 MARVEL DELACRUZ
Applicant returned to address corrections 2/3/2021 MARVEL DELACRUZ
Applicant returned to address corrections 9/1/2021 MARVEL DELACRUZ
Plan Check Approved 9/1/2021 MARVEL DELACRUZ
Issued 9/28/2021 APPLICANT
Permit Finaled 5/21/2025 ALEXANDER HELFER

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Razmik Construction Inc; Lic. No.: 544544-B 3571 E CHEVY CHASE DR      GLENDALE, CA 91206

Inspector Information

BRIAN MILLER, (818) 374-4359 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 11/9/2021 Approved TIMOTHY POWELL
Special/Order Compliance 3/23/2022 Corrections Issued VASIL MIHALEV
Special/Order Compliance 4/6/2022 Partial Inspection BRIAN MILLER
Initial Grading 5/11/2022 No Access for Inspection LANNY MERRICK
Sub-Drain 5/11/2022 Not Ready for Inspection LANNY MERRICK
Sub-Drain 5/13/2022 Partial Approval LANNY MERRICK
Bottom/Toe 8/23/2022 Approved LANNY MERRICK
Approved Compaction Report 5/2/2025 Corrections Issued MANUEL TEJADA
Approved Compaction Report 5/13/2025 Approved MANUEL TEJADA
Final 5/21/2025 Permit Finaled ALEXANDER HELFER
Rough 5/21/2025 Approved ALEXANDER HELFER