7752 S AIRPORT BLVD 90045
Certificate Information: 7752 S AIRPORT BLVD 90045
- Application / Permit
- 19030-20000-07098
- Plan Check / Job No.
- B19VN19033
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- Grading permit for retaining wall excavation and backfill.
- Permit Issued
- Issued on 6/26/2020
- Issuing Office
- Current Status
- Permit Finaled on 11/13/2025
Permit Application Status History
| Submitted | 11/1/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/14/2019 | ALDOUS CHIC |
| Corrections Issued | 11/18/2019 | ALDOUS CHIC |
| Quality Review Completed | 11/19/2019 | ABDUL CHEGENI |
| Building Plans Picked Up | 11/20/2019 | APPLICANT |
| Applicant returned to address corrections | 5/4/2020 | RODNEY SAMIIAN |
| Applicant returned to address corrections | 6/12/2020 | RODNEY SAMIIAN |
| Plan Check Approved | 6/26/2020 | RODNEY SAMIIAN |
| Issued | 6/26/2020 | APPLICANT |
| Permit Finaled | 11/12/2025 | MATTHEW JENKINS |
Permit Application Clearance Information
| Miscellaneous | Cleared | 5/4/2020 | ALDOUS CHIC |
Contact Information
| Contractor | L J Properties Inc; Lic. No.: 968120-B | 3501 OCEAN VIEW BLVD GLENDALE, CA 91208 |
| Engineer | Miller,, Karen Lynn; Lic. No.: GE2257 | 6634 VALJEAN AVE VAN NUYS, CA 91406 |
| Engineer | Samara,, Muzahim Ali; Lic. No.: C26015 | 9100 S SEPULVEDA BLVD SUITE 115 LOS ANGELES, CA 90045 |
Inspector Information
| JESUS RODRIGUEZ, (213) 216-1187 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation | 8/25/2020 | Approved | JONATHAN HOM |
| Initial Grading | 8/25/2020 | Approved | JONATHAN HOM |
| Drainage Devices/Catch Basin | 9/1/2020 | Approved | JONATHAN HOM |
| Rough | 9/15/2020 | Approved | JONATHAN HOM |
| Special/Order Compliance | 9/15/2020 | Partial Inspection | JONATHAN HOM |
| Bottom/Toe | 11/5/2020 | Approved | JONATHAN HOM |
| Rough | 11/10/2020 | Conditional Approval | JONATHAN HOM |
| Sub-Drain | 11/10/2020 | Partial Inspection | JONATHAN HOM |
| Rough | 11/25/2020 | Partial Inspection | MATTHEW JENKINS |
| Sub-Drain | 1/7/2021 | Partial Approval | KIRK LINKLATER |
| Special/Order Compliance | 4/16/2021 | Partial Inspection | JONATHAN HOM |
| Approved Compaction Report | 8/18/2022 | Approved | JONATHAN HOM |
| Approved Compaction Report | 7/26/2024 | Corrections Issued | MATTHEW JENKINS |
| Approved Compaction Report | 8/8/2024 | Corrections Issued | MATTHEW JENKINS |
| Final | 9/18/2024 | Not Ready for Inspection | AL GAMBLE |
| Rough | 9/18/2024 | Not Ready for Inspection | AL GAMBLE |
| Final | 9/24/2024 | Partial Inspection | MATTHEW JENKINS |
| Rough | 9/24/2024 | Partial Inspection | MATTHEW JENKINS |
| Rough | 9/26/2024 | Partial Inspection | MATTHEW JENKINS |
| Special/Order Compliance | 10/15/2024 | Approved | VASIL MIHALEV |
| Final | 9/2/2025 | Partial Inspection | MATTHEW JENKINS |
| Rough | 9/2/2025 | Partial Inspection | MATTHEW JENKINS |
| Final | 11/12/2025 | Permit Finaled | MATTHEW JENKINS |
| Rough | 11/12/2025 | Approved | MATTHEW JENKINS |