4030 N MADELIA AVE 91403

Certificate Information: 4030 N MADELIA AVE 91403

Application / Permit
19030-20000-06932
Plan Check / Job No.
B19VN18559
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
SITE GRADING FOR NEW 1-STORY SFD W/ ATTACHED 2-CAR GARAGE AND BASEMENT ON PILES AND RETAINING WALLS
Permit Issued
Issued on 10/26/2020
Issuing Office
Valley
Current Status
Permit Finaled on 8/29/2022

Permit Application Status History

Submitted 10/28/2019 APPLICANT
Assigned to Plan Check Engineer 11/21/2019 JENNIFER LEE
Corrections Issued 11/26/2019 JENNIFER LEE
Quality Review Completed 11/27/2019 GUANG MIN TUNG
Building Plans Picked Up 12/3/2019 APPLICANT
Green Plans Picked Up 12/17/2019 APPLICANT
Applicant returned to address corrections 5/29/2020 JENNIFER LEE
Applicant returned to address corrections 9/14/2020 JENNIFER LEE
Applicant returned to address corrections 9/16/2020 JENNIFER LEE
Plan Check Approved 10/20/2020 JENNIFER LEE
Issued 10/26/2020 APPLICANT
Permit Finaled 8/29/2022 VASIL MIHALEV

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,
Geologist Schick,, John Wayne; Lic. No.: EG1300 7650 HASKELL AVENUE STE D      VAN NUYS, CA 91406

Inspector Information

MATTHEW JENKINS, (818) 374-4357 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Drainage Devices/Catch Basin 1/13/2021 Corrections Issued TIMOTHY POWELL
Drainage Devices/Catch Basin 1/14/2021 Not Ready for Inspection TIMOTHY POWELL
Special/Order Compliance 1/14/2021 Partial Approval TIMOTHY POWELL
Sub-Drain 1/19/2021 Corrections Issued VASIL MIHALEV
Drainage Devices/Catch Basin 1/21/2021 Conditional Approval VASIL MIHALEV
Sub-Drain 4/7/2021 Not Ready for Inspection TIMOTHY POWELL
Sub-Drain 4/29/2021 Partial Approval KIRK LINKLATER
Sub-Drain 7/6/2021 Not Ready for Inspection MANUEL TEJADA
Sub-Drain 7/7/2021 Partial Approval MANUEL TEJADA
Bottom/Toe 8/29/2022 Approved VASIL MIHALEV
Final 8/29/2022 Not Ready for Inspection VASIL MIHALEV
Final 8/29/2022 Permit Finaled VASIL MIHALEV
Rough 8/29/2022 Approved VASIL MIHALEV