10132 N COMMERCE AVE #1-37 91042
Certificate Information: 10132 N COMMERCE AVE #1-37 91042
- Application / Permit
- 19030-20000-06158
- Plan Check / Job No.
- B19VN16259
- Group
- Building
- Type
- Grading
- Sub-Type
- Apartment
- Primary Use
- (70) Grading - Hillside
- Work Description
- EXCAVATION & BACKFILL FOR (N) 3-STORY OVER BASEMENT PARKING GARAGE -- HILLSIDE GRADING AREA
- Permit Issued
- Issued on 2/19/2021
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 11/2/2023
Permit Application Status History
| Submitted | 9/24/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/17/2019 | NILOOFAR MEHRAIN |
| Disabled Access Plans Picked Up | 10/29/2019 | APPLICANT |
| Green Plans Picked Up | 10/29/2019 | APPLICANT |
| Corrections Issued | 10/30/2019 | NILOOFAR MEHRAIN |
| Quality Review Completed | 10/31/2019 | GUANG MIN TUNG |
| Building Plans Picked Up | 11/5/2019 | APPLICANT |
| Applicant returned to address corrections | 8/11/2020 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 11/6/2020 | NILOOFAR MEHRAIN |
| Plan Check Approved | 1/26/2021 | NILOOFAR MEHRAIN |
| Issued | 2/19/2021 | APPLICANT |
| Permit Finaled | 11/1/2023 | MANUEL TEJADA |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/10/2020 | APEKSHYA BAJRACHARYA |
| Roof/Waste drainage to street | Cleared | 10/15/2020 | GABRIEL ROBLES |
| Miscellaneous | Cleared | 1/20/2021 | DANG NGUYEN |
| Specific Plan | Cleared | 1/20/2021 | DANG NGUYEN |
| ZI | Cleared | 1/20/2021 | DANG NGUYEN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Motavvef,, Nasser; Lic. No.: C40977 | 15335 MORRISON ST 370 SHERMAN OAKS, CA 91403 |
Inspector Information
| BRIAN MILLER, (818) 374-4359 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 3/3/2021 | Approved | TIMOTHY POWELL |
| Special/Order Compliance | 3/10/2021 | Partial Inspection | TIMOTHY POWELL |
| Bottom/Toe | 7/2/2021 | Not Ready for Inspection | ALEXANDER HELFER |
| Sub-Drain | 7/2/2021 | Approved | ALEXANDER HELFER |
| Drainage Devices/Catch Basin | 10/6/2021 | Partial Approval | BRIAN MILLER |
| Special/Order Compliance | 1/5/2022 | Approved | BRIAN MILLER |
| Special/Order Compliance | 1/10/2022 | Approved | BRIAN MILLER |
| Drainage Devices/Catch Basin | 6/1/2023 | Partial Approval | MICHAEL TEMPLE |
| Irrigation/Landscape | 10/31/2023 | Partial Inspection | GERMAN RODRIGUEZ MENDOZA |
| Bottom/Toe | 11/1/2023 | Approved | MANUEL TEJADA |
| Final | 11/1/2023 | Permit Finaled | MANUEL TEJADA |
| Rough | 11/1/2023 | Approved | MANUEL TEJADA |