10205 N SUNLAND BLVD 91040
Certificate Information: 10205 N SUNLAND BLVD 91040
- Application / Permit
- 19030-20000-04597
- Plan Check / Job No.
- B19VN11959
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- SITE PREP AND BACKFILL, EXCAVATION FOR (N) POOL ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 3/18/2021
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 3/25/2022
Permit Application Status History
| Submitted | 7/18/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/15/2019 | ALYSSA N NARCISO |
| Corrections Issued | 8/28/2019 | ALYSSA N NARCISO |
| Quality Review Completed | 8/29/2019 | CHON CHIO KUO |
| Building Plans Picked Up | 8/29/2019 | APPLICANT |
| Applicant returned to address corrections | 3/11/2020 | ALYSSA N NARCISO |
| Applicant returned to address corrections | 7/28/2020 | ALYSSA N NARCISO |
| Applicant returned to address corrections | 3/2/2021 | SEWADA ZADOORIAN MILAGARDI |
| Application Withdrawn-Void | 3/8/2021 | OMID HEDAYAT |
| Re-Activate Application | 3/8/2021 | OMID HEDAYAT |
| Plan Check Approved | 3/18/2021 | OMID HEDAYAT |
| Issued | 3/18/2021 | APPLICANT |
| Permit Finaled | 3/24/2022 | BRIAN MILLER |
Permit Application Clearance Information
| Specific Plan | Cleared | 11/25/2019 | PEGGY MALONE-BROWN |
| Miscellaneous | Cleared | 2/21/2020 | STEVEN WECHSLER |
| Miscellaneous | Cleared | 2/21/2020 | STEVEN WECHSLER |
| Grading Pre-Inspection | Cleared | 3/8/2021 | ALYSSA N NARCISO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
| Engineer | Mahn,, Jonathan Edward; Lic. No.: C60293 | 12848 FOOTHILL BLVD SYLMAR, CA 91381 |
| Geologist | Triebold,, Mark John; Lic. No.: EG1796 | 6906 QUITO COURT CAMARILLO, CA 93012 |
Inspector Information
| BRIAN MILLER, (818) 374-4359 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Bottom/Toe | 4/13/2021 | Approved | KIRK LINKLATER |
| Excavation | 4/13/2021 | Approved | KIRK LINKLATER |
| Rough | 7/6/2021 | Partial Inspection | MANUEL TEJADA |
| Final | 3/24/2022 | Permit Finaled | BRIAN MILLER |
| Rough | 3/24/2022 | Approved | BRIAN MILLER |