453 N STANLEY AVE 90036
Certificate Information: 453 N STANLEY AVE 90036
- Application / Permit
- 19030-20000-04500
- Plan Check / Job No.
- B19VN11723
- Group
- Building
- Type
- Grading
- Sub-Type
- Apartment
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- Remove and Recompact under proposed building foundation.
- Permit Issued
- Issued on 4/29/2021
- Issuing Office
- Current Status
- Permit Finaled on 12/5/2024
Permit Application Status History
| Submitted | 7/16/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/16/2019 | OMID HEDAYAT |
| Corrections Issued | 7/16/2019 | OMID HEDAYAT |
| Applicant returned to address corrections | 10/23/2019 | OMID HEDAYAT |
| Plan Check Approved | 10/23/2019 | OMID HEDAYAT |
| Issued | 4/29/2021 | APPLICANT |
| Permit Finaled | 12/4/2024 | JONATHAN HOM |
Permit Application Clearance Information
| Historic monument | Cleared | 10/23/2019 | MELISSA JONES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chan,, Christopher Charles; Lic. No.: C30282 | 2567 SALEROSO DR ROWLAND HEIGHTS, CA 91748 |
| Geologist | Kennedy,, Cameron L; Lic. No.: EG2631 | 25208 W DOLCE COURT STEVENSON RANCH, CA 91381 |
Inspector Information
| AL GAMBLE, (213) 482-0403 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation | 1/12/2022 | Not Ready for Inspection | ALEXANDER HELFER |
| Initial Grading | 1/12/2022 | Approved | ALEXANDER HELFER |
| Bottom/Toe | 2/9/2022 | Partial Approval | ALEXANDER HELFER |
| Deputy Grading | 2/9/2022 | Conditional Approval | LANNY MERRICK |
| Deputy Grading | 2/10/2022 | Conditional Approval | LANNY MERRICK |
| Bottom/Toe | 2/11/2022 | Partial Approval | LANNY MERRICK |
| Deputy Grading | 2/11/2022 | Conditional Approval | LANNY MERRICK |
| Excavation | 2/16/2022 | Partial Approval | LANNY MERRICK |
| Bottom/Toe | 2/23/2022 | Conditional Approval | LANNY MERRICK |
| Excavation | 2/28/2022 | Partial Approval | LANNY MERRICK |
| Bottom/Toe | 3/1/2022 | Partial Approval | LANNY MERRICK |
| Deputy Grading | 3/2/2022 | Conditional Approval | LANNY MERRICK |
| Deputy Grading | 3/3/2022 | Conditional Approval | LANNY MERRICK |
| Rough | 3/7/2022 | Partial Inspection | MATTHEW JENKINS |
| Bottom/Toe | 3/9/2022 | Partial Approval | LANNY MERRICK |
| Approved Compaction Report | 4/13/2022 | Partial Inspection | ALEXANDER HELFER |
| Initial Grading | 4/13/2022 | Corrections Issued | ALEXANDER HELFER |
| Approved Compaction Report | 5/5/2022 | Approved | MATTHEW JENKINS |
| Approved Compaction Report | 5/13/2022 | Not Ready for Inspection | ALEXANDER HELFER |
| Drainage Devices/Catch Basin | 5/13/2022 | Not Ready for Inspection | ALEXANDER HELFER |
| Special/Order Compliance | 5/13/2022 | Not Ready for Inspection | ALEXANDER HELFER |
| Drainage Devices/Catch Basin | 11/28/2022 | Partial Approval | JONATHAN HOM |
| Bottom/Toe | 12/4/2024 | Approved | JONATHAN HOM |
| Final | 12/4/2024 | Permit Finaled | JONATHAN HOM |
| Rough | 12/4/2024 | Approved | JONATHAN HOM |