14055 N BALBOA BLVD 91342

Certificate Information: 14055 N BALBOA BLVD 91342

Application / Permit
19030-20000-04378
Plan Check / Job No.
B19VN11408
Group
Building
Type
Grading
Sub-Type
Commercial
Primary Use
(70) Grading - Hillside
Work Description
GRADING WORK FOR RETAINING WALLS
Permit Issued
Issued on 7/29/2021
Issuing Office
Valley
Current Status
Permit Finaled on 5/1/2025

Permit Application Status History

Submitted 7/11/2019 APPLICANT
Assigned to Plan Check Engineer 8/15/2019 RODNEY SAMIIAN
Corrections Issued 8/21/2019 RODNEY SAMIIAN
Quality Review Completed 8/21/2019 ABDUL CHEGENI
Building Plans Picked Up 8/23/2019 APPLICANT
Applicant returned to address corrections 6/26/2020 RODNEY SAMIIAN
Applicant returned to address corrections 2/23/2021 RODNEY SAMIIAN
Applicant returned to address corrections 3/17/2021 RODNEY SAMIIAN
Applicant returned to address corrections 6/18/2021 MARVEL DELACRUZ
Plan Check Approved 7/16/2021 MARVEL DELACRUZ
Issued 7/29/2021 APPLICANT
Permit Finaled 4/30/2025 CHARLES POWELL

Permit Application Clearance Information

Low Impact Development Cleared 6/1/2020 MARTIN FRAGOSO
Address approval Cleared 6/8/2020 HOWARD COOPER
Eng Process Fee Ord 176,300 Cleared 7/20/2020 ELENA LOPEZ
Permit Cleared 9/23/2020 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 2/11/2021 LEE GUILBEAUX
"Q" conditions Cleared 3/5/2021 JOE LUCKEY
"T" removal Cleared 3/5/2021 JOE LUCKEY
ZA Case Cleared 3/5/2021 JOE LUCKEY
Grading Pre-Inspection Cleared 3/17/2021 ABDUL CHEGENI
Miscellaneous Cleared 3/17/2021 ABDUL CHEGENI

Contact Information

Contractor Maely Inc; Lic. No.: 890900-A 4037 PHELAN ROAD #A-269      PHELAN, CA 92371
Engineer Farmer,, Douglas Dale; Lic. No.: C49041 649 FOWLER AVE      NEWBURY PARK, CA 91320

Inspector Information

BRIAN MILLER, (818) 374-4359 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 10/5/2021 Corrections Issued BRIAN MILLER
Initial Grading 10/28/2021 Approved BRIAN MILLER
Excavation 11/4/2021 Partial Inspection BRIAN MILLER
Excavation 11/5/2021 Partial Approval TIMOTHY POWELL
Approved Compaction Report 3/16/2023 Not Ready for Inspection ROBERT PINA
Initial Grading 2/7/2024 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Approved Compaction Report 3/20/2024 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Approved Compaction Report 4/9/2024 Approved GERMAN RODRIGUEZ MENDOZA
Sub-Drain 4/24/2024 Partial Approval GERMAN RODRIGUEZ MENDOZA
Sub-Drain 4/30/2024 Partial Approval CHARLES POWELL
Sub-Drain 6/5/2024 Partial Approval GERMAN RODRIGUEZ MENDOZA
Drainage Devices/Catch Basin 9/17/2024 Partial Approval CHARLES POWELL
Drainage Devices/Catch Basin 9/18/2024 Partial Approval CHARLES POWELL
Drainage Devices/Catch Basin 12/6/2024 Partial Approval CHARLES POWELL
Approved Compaction Report 4/3/2025 Approved MANUEL TEJADA
Bottom/Toe 4/11/2025 Approved GERMAN RODRIGUEZ MENDOZA
Final 4/11/2025 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Rough 4/11/2025 Approved GERMAN RODRIGUEZ MENDOZA
Final 4/30/2025 Permit Finaled CHARLES POWELL