509 N MOUNT HOLYOKE AVE 90272

Certificate Information: 509 N MOUNT HOLYOKE AVE 90272

Application / Permit
19030-20000-04236
Plan Check / Job No.
B19VN11034
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
REMOVE & RECOMPACT UNDER 3-CAR GARAGE, EXCAVATION FOR CONCRETE PILES TO SUPPORT 3-CAR GARAGE AND BACKFILL (2) RETAINING WALLS.
Permit Issued
Issued on 2/6/2020
Issuing Office
Valley
Current Status
Permit Finaled on 9/22/2023

Permit Application Status History

Submitted 7/3/2019 APPLICANT
Assigned to Plan Check Engineer 7/25/2019 GURUNATH NESARAJAH
Corrections Issued 7/27/2019 GURUNATH NESARAJAH
Quality Review Completed 7/30/2019 OMID HEDAYAT
Building Plans Picked Up 8/2/2019 APPLICANT
Green Plans Picked Up 8/2/2019 APPLICANT
Plan Check Approved 1/24/2020 GURUNATH NESARAJAH
Issued 2/6/2020 LADBS
Permit Finaled 9/21/2023 JOHNNY MIRANDA

Permit Application Clearance Information

Coastal Zone Cleared 9/23/2019 SARAH GOLDMAN
ZI Cleared 9/23/2019 SARAH GOLDMAN
GPI Written Notices Cleared 10/24/2019 GURUNATH NESARAJAH
Grading Pre-Inspection Cleared 10/24/2019 GURUNATH NESARAJAH

Contact Information

Architect Kerr,, Robert E; Lic. No.: C28038 2551 S BUNDY DRIVE      LOS ANGELES, CA 90064
Contractor Scanlon Construction Inc; Lic. No.: 629700-B 10650 OVERMAN AVENUE      CHATSWORTH, CA 91311
Engineer Irvine,, Jon Alan; Lic. No.: GE2891 145 N SIERRA MADRE BLVD STE 1      PASADENA, CA 91107
Engineer Mahlow,, Elizabeth Joy Johnson; Lic. No.: C80463 4215 TOLAND WAY      LOS ANGELES, CA 90065

Inspector Information

RUSSELL BONVOULOIR, (310) 914-3899 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Grading 2/24/2020 Partial Approval MATTHEW JENKINS
Deputy Grading 2/25/2020 Conditional Approval MATTHEW JENKINS
Deputy Grading 2/26/2020 Partial Approval MATTHEW JENKINS
Drainage Devices/Catch Basin 7/2/2020 Partial Approval MATTHEW JENKINS
Drainage Devices/Catch Basin 7/16/2020 Partial Approval MATTHEW JENKINS
Drainage Devices/Catch Basin 12/17/2020 Corrections Issued BRIAN OLSON
Rough 6/30/2021 Corrections Issued MATTHEW JENKINS
Special/Order Compliance 4/28/2022 Partial Inspection TIMOTHY POWELL
Special/Order Compliance 5/10/2022 Partial Inspection TIMOTHY POWELL
Special/Order Compliance 5/26/2022 Partial Inspection TIMOTHY POWELL
Special/Order Compliance 6/9/2022 Not Ready for Inspection TIMOTHY POWELL
Bottom/Toe 8/28/2023 Partial Inspection JOHNNY MIRANDA
Final 8/28/2023 Partial Inspection JOHNNY MIRANDA
Rough 8/28/2023 Partial Inspection JOHNNY MIRANDA
Bottom/Toe 9/21/2023 Approved JOHNNY MIRANDA
Final 9/21/2023 Permit Finaled JOHNNY MIRANDA
Rough 9/21/2023 Approved JOHNNY MIRANDA