4021 N ROYAL OAK PL 91436

Certificate Information: 4021 N ROYAL OAK PL 91436

Application / Permit
19030-20000-03821
Plan Check / Job No.
B19VN09920
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
(4 OF 4) SITE GRADING, EXCAVATE BADEMENT/RETAINING WALL, & CUT1571CY, FILL 816 CY, EXPORT 831CY.
Permit Issued
Issued on 1/3/2020
Issuing Office
Valley
Current Status
Permit Finaled on 2/3/2022

Permit Application Status History

Submitted 6/14/2019 APPLICANT
Green Plans Picked Up 6/25/2019 APPLICANT
Assigned to Plan Check Engineer 7/11/2019 CHON CHIO KUO
Corrections Issued 7/15/2019 CHON CHIO KUO
Quality Review Completed 7/17/2019 STEVEN KIM
Building Plans Picked Up 7/17/2019 APPLICANT
Applicant returned to address corrections 8/13/2019 CHON CHIO KUO
Applicant returned to address corrections 9/12/2019 CHON CHIO KUO
Plan Check Approved 12/20/2019 CHON CHIO KUO
Issued 1/3/2020 LADBS
Permit Finaled 2/2/2022 ALEXANDER ANDREWS

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 7/24/2019 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 7/24/2019 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 7/24/2019 LEE GUILBEAUX
Miscellaneous Cleared 7/24/2019 LEE GUILBEAUX
Permit Cleared 7/24/2019 LEE GUILBEAUX
Work Adjacent to Public Way Cleared 7/24/2019 LEE GUILBEAUX
GPI Written Notices Cleared 8/13/2019 CHON CHIO KUO
Grading Pre-Inspection Cleared 8/13/2019 CHON CHIO KUO
Low Impact Development Cleared 8/21/2019 MITESH PATEL
BHO/Hillside ordinance Cleared 8/26/2019 JOSHUA DIAZ
Roof/Waste drainage to street Cleared 8/26/2019 JOSHUA DIAZ
Excavation more than 5-ft deep Cleared 9/12/2019 CALOSHA APPROVED
Disturb/Remove Protected Trees Cleared 12/18/2019 JOHN KIM
Trees in Parkway Cleared 12/18/2019 JOHN KIM

Contact Information

Contractor Owner-Builder       ,
Engineer Nazari,, Arthur; Lic. No.: C53497 PO BOX 7112      NORTHRIDGE, CA 91327

Inspector Information

MANUEL TEJADA, (818) 374-4339 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 2/3/2020 Approved ALEXANDER ANDREWS
Deputy Grading 2/12/2020 Approved ALEXANDER ANDREWS
Deputy Grading 2/13/2020 Approved ALEXANDER ANDREWS
Deputy Grading 2/14/2020 Conditional Approval TIMOTHY POWELL
Deputy Grading 2/18/2020 Approved ALEXANDER ANDREWS
Deputy Grading 2/20/2020 Approved ALEXANDER ANDREWS
Deputy Grading 2/24/2020 Approved ALEXANDER ANDREWS
Deputy Grading 3/20/2020 Approved ALEXANDER ANDREWS
Deputy Grading 3/24/2020 Approved ALEXANDER ANDREWS
Drainage Devices/Catch Basin 8/11/2020 Partial Approval ALEXANDER ANDREWS
Sub-Drain 8/11/2020 Partial Approval ALEXANDER ANDREWS
Drainage Devices/Catch Basin 9/14/2020 Partial Approval ALEXANDER ANDREWS
Rough 9/30/2020 Not Ready for Inspection TIMOTHY POWELL
Sub-Drain 9/30/2020 Not Ready for Inspection TIMOTHY POWELL
Excavation 10/1/2020 Not Ready for Inspection TIMOTHY POWELL
Sub-Drain 10/26/2020 Partial Approval ALEXANDER ANDREWS
Approved Compaction Report 7/1/2021 Approved TIMOTHY POWELL
Approved Compaction Report 7/1/2021 Partial Inspection ALEXANDER HELFER
Bottom/Toe 2/2/2022 Approved ALEXANDER ANDREWS
Final 2/2/2022 Permit Finaled ALEXANDER ANDREWS
Rough 2/2/2022 Approved ALEXANDER ANDREWS