4293 N TUJUNGA AVE 91604
Certificate Information: 4293 N TUJUNGA AVE 91604
- Application / Permit
- 19030-20000-03293
- Plan Check / Job No.
- B19VN08626
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- NEW GRADING FOR SITE PREPARATION
- Permit Issued
- Issued on 9/25/2020
- Issuing Office
- Current Status
- Permit Finaled on 8/18/2022
Permit Application Status History
| Submitted | 5/24/2019 | APPLICANT |
| Green Plans Picked Up | 6/7/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/13/2019 | RARES BODEA |
| Corrections Issued | 6/16/2019 | RARES BODEA |
| Quality Review Completed | 6/18/2019 | OMID HEDAYAT |
| Building Plans Picked Up | 6/18/2019 | APPLICANT |
| Applicant returned to address corrections | 7/9/2019 | RARES BODEA |
| Applicant returned to address corrections | 7/23/2019 | RARES BODEA |
| Applicant returned to address corrections | 8/9/2019 | RARES BODEA |
| Applicant returned to address corrections | 1/21/2020 | RARES BODEA |
| Plan Check Approved | 2/13/2020 | RARES BODEA |
| Issued | 9/25/2020 | APPLICANT |
| Permit Finaled | 8/18/2022 | MANUEL TEJADA |
Permit Application Clearance Information
| "Q" conditions | Cleared | 6/24/2019 | ANNA VAN |
| "T" removal | Cleared | 2/10/2020 | JOE LUCKEY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW JENKINS, (818) 374-4357 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Bottom/Toe | 10/6/2020 | Partial Approval | TIMOTHY POWELL |
| Excavation | 10/6/2020 | Partial Approval | TIMOTHY POWELL |
| Initial Grading | 10/6/2020 | Approved | TIMOTHY POWELL |
| Bottom/Toe | 10/13/2020 | Partial Inspection | TIMOTHY POWELL |
| Excavation | 10/13/2020 | Partial Inspection | TIMOTHY POWELL |
| Approved Compaction Report | 11/10/2020 | Approved | MANUEL TEJADA |
| Initial Grading | 6/2/2021 | Approved | ALEXANDER HELFER |
| Excavation | 6/3/2021 | Partial Approval | MATTHEW JENKINS |
| Bottom/Toe | 6/4/2021 | Approved | KIRK LINKLATER |
| Deputy Grading | 6/9/2021 | Approved | KIRK LINKLATER |
| Excavation | 6/9/2021 | Partial Approval | KIRK LINKLATER |
| Final | 8/9/2022 | Corrections Issued | MANUEL TEJADA |
| Rough | 8/9/2022 | Approved | MANUEL TEJADA |
| Approved Compaction Report | 8/17/2022 | Approved | MANUEL TEJADA |
| Final | 8/18/2022 | Permit Finaled | MANUEL TEJADA |