8812 W YATES ST 91040
Certificate Information: 8812 W YATES ST 91040
- Application / Permit
- 19030-20000-02653
- Plan Check / Job No.
- B19VN06844
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- EXCAVATION AND BACKFILL FOR PROPOSED ACCESSORY DWELLING UNIT, POOL AND RETAINING WALL."COMPLY WITH DEPARTMENT ORDER effective date 08/21/2018. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 9/9/2020
- Issuing Office
- Current Status
- Permit Finaled on 4/2/2024
Permit Application Status History
| Submitted | 4/26/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/30/2019 | SARKIS HARABEDIAN |
| Green Plans Picked Up | 5/30/2019 | APPLICANT |
| Corrections Issued | 6/14/2019 | SARKIS HARABEDIAN |
| Quality Review Completed | 6/24/2019 | ABDUL CHEGENI |
| Building Plans Picked Up | 6/25/2019 | APPLICANT |
| Applicant returned to address corrections | 9/6/2019 | SARKIS HARABEDIAN |
| Applicant returned to address corrections | 9/18/2019 | SARKIS HARABEDIAN |
| Plan Check Approved | 10/17/2019 | SARKIS HARABEDIAN |
| Issued | 9/9/2020 | APPLICANT |
| Permit Finaled | 4/2/2024 | GERMAN RODRIGUEZ MENDOZA |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/9/2019 | SARKIS HARABEDIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Alrayes,, Nidham Aram; Lic. No.: C65487 | 10346 SAMOA AVE TUJUNGA, CA 91042 |
| Engineer | Babakhanian,, Oksen; Lic. No.: S3500 | 6854 FOOTHILL BLVD TUJUNGA, CA 91042 |
| Engineer | Mkrtchyan,, Gor; Lic. No.: L7387 | 16730 CANTLAY ST VAN NUYS, CA 91406 |
| Geologist | Haney,, Harry Drew; Lic. No.: EG2091 | 9003 DE SOTO AVENUE CANOGA PARK, CA 91304 |
Inspector Information
| MATTHEW JENKINS, (818) 374-4357 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Bottom/Toe | 11/20/2020 | Not Ready for Inspection | TIMOTHY POWELL |
| Excavation | 11/20/2020 | Corrections Issued | TIMOTHY POWELL |
| Special/Order Compliance | 12/4/2020 | Partial Inspection | TIMOTHY POWELL |
| Sub-Drain | 12/15/2020 | Partial Approval | TIMOTHY POWELL |
| Special/Order Compliance | 12/31/2020 | Order to Comply Issued | TIMOTHY POWELL |
| Excavation | 1/6/2021 | Conditional Approval | VASIL MIHALEV |
| Approved Compaction Report | 2/1/2024 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Bottom/Toe | 4/2/2024 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Final | 4/2/2024 | Permit Finaled | GERMAN RODRIGUEZ MENDOZA |
| Rough | 4/2/2024 | Approved | GERMAN RODRIGUEZ MENDOZA |