3726 N LATROBE ST 90031
Certificate Information: 3726 N LATROBE ST 90031
- Application / Permit
- 19030-20000-00378
- Plan Check / Job No.
- B19VN00982
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- SITE GRADING FOR NEW THREE STORY SINGLE FAMILY DWELLING WITH BASEMENT GARAGE AND BACKFILL FOR PROPOSED RETAINING WALL.
- Permit Issued
- Issued on 7/5/2024
- Issuing Office
- Valley
- Current Status
- Issued on 7/5/2024
Permit Application Status History
| Submitted | 1/22/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/14/2019 | SARKIS HARABEDIAN |
| Green Plans Picked Up | 2/21/2019 | APPLICANT |
| Corrections Issued | 2/25/2019 | SARKIS HARABEDIAN |
| Quality Review Completed | 3/1/2019 | OMID HEDAYAT |
| Applicant returned to address corrections | 7/16/2019 | SARKIS HARABEDIAN |
| Applicant returned to address corrections | 8/20/2019 | SARKIS HARABEDIAN |
| Applicant returned to address corrections | 10/8/2019 | SARKIS HARABEDIAN |
| Applicant returned to address corrections | 3/17/2021 | SARKIS HARABEDIAN |
| Building Plans Picked Up | 3/18/2021 | APPLICANT |
| Applicant returned to address corrections | 9/23/2022 | SARKIS HARABEDIAN |
| Plan Check Approved | 9/26/2022 | SARKIS HARABEDIAN |
| Issued | 7/5/2024 | APPLICANT |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Evangelista,, Gil Viernes; Lic. No.: S2422 | 749 N FEATHERWOOD DR DIAMOND BAR, CA 91765 |
| Engineer | Salehipour,, Sassan Abolghasem; Lic. No.: C44172 | 1290 NORTH LAKE AVENUE STE 204 PASADENA, CA 91104 |
Inspector Information
| JONATHAN HOM, (213) 482-7452 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT HUGHES, (213) 482-7452 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 8/9/2024 | Approved | LANNY MERRICK |
| Sub-Drain | 9/30/2024 | Partial Approval | LANNY MERRICK |
| Bottom/Toe | 10/25/2024 | Partial Inspection | LANNY MERRICK |
| Sub-Drain | 11/18/2024 | Not Ready for Inspection | LANNY MERRICK |
| Fill/Backfill | 11/19/2024 | Partial Approval | LANNY MERRICK |
| Sub-Drain | 1/21/2025 | Partial Approval | RUSSELL BONVOULOIR |
| Bottom/Toe | 4/14/2025 | Corrections Issued | RUSSELL BONVOULOIR |
| Rough | 4/16/2025 | Partial Inspection | RUSSELL BONVOULOIR |
| Bottom/Toe | 4/22/2025 | Partial Approval | MICHAEL TEMPLE |
| Excavation | 4/29/2025 | Partial Approval | RAMAZANALI ALMASI |
| Sub-Drain | 6/9/2025 | Partial Approval | ROBERT PINA |
| Private Sewage Disposal System | 7/21/2025 | Corrections Issued | RAMAZANALI ALMASI |
| Private Sewage Disposal System | 7/23/2025 | Partial Inspection | JONATHAN HOM |